After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run.
What two actions should the project manager take? (Choose two.)

  • A. Send a questionnaire to the project participants and seek their feedback.
  • B. Refer to the communications management plan.
  • C. Obtain official approval on the new process from the various countries.
  • D. Prepare the lessons learned from the project phase.
  • E. Deliver the project materials to the users and see if they have any comments.
Show Suggested Answer Hide Answer
Suggested Answer: AD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Musaad
9 months, 2 weeks ago
Selected Answer: AB
project is completed meaning lesson learned already summited not prepare LL from project phase!!. although project phase is not mentioned in Q
upvoted 3 times
...
Bruce_Liu
9 months, 3 weeks ago
Selected Answer: AD
AD is the direct answer. B is too general not essential.
upvoted 1 times
...
josephsafiran
9 months, 3 weeks ago
Selected Answer: AD
The project manager should choose options A. Send a questionnaire to the project participants and seek their feedback and D. Prepare the lessons learned from the project phase. Option A allows the project manager to directly gauge user satisfaction and gather valuable feedback. Option D helps in documenting the experiences, successes, and challenges faced during the project, which can be used for future reference and continuous improvement. Both these actions would provide insights into the users’ satisfaction with the project.
upvoted 2 times
...
princeviper
12 months ago
Selected Answer: AB
A and B are the steps PM have to do "right away". Although it is plausible, D is the "next (next) step". Therefore, A and B
upvoted 1 times
...
Satyabrata_Paul
1 year ago
If you choose A, then option B is also the correct answer. Option B will guide you on how to send the questionnaires to the users (through email, embedding them in some websites, over phone etc) which will be guided by the communication plan.
upvoted 2 times
...
Only12go
1 year ago
Selected Answer: AD
A. Send a questionnaire to the project participants and seek their feedback. This direct method of seeking feedback will provide insights into the satisfaction levels of the project users. D. Prepare the lessons learned from the project phase. Lessons learned is a compilation of the knowledge and experiences gained during the project. Reviewing the lessons learned can give an idea of what went well and what could have been improved, which in turn can provide insights into user satisfaction.
upvoted 1 times
...
kevzzz
1 year ago
Selected Answer: AD
This is a lessons learned question. The person who will be facilitating the lessons learned session should prepare in advance. In preparation for the lessons learned session the facilitator should have the participants complete a project survey. https://www.pmi.org/learning/library/lessons-learned-next-level-communicating-7991#:~:text=Lessons%20learned%20are%20the%20documented,the%20actual%20experiences%20of%20others.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: AD
A. Send a questionnaire to the project participants and seek their feedback D. Prepare the lessons learned from the project phase
upvoted 1 times
...
JYKL88
1 year, 5 months ago
Selected Answer: AB
will go with AB
upvoted 2 times
...
JMCCRAY
1 year, 6 months ago
Selected Answer: AD
The project manager should take the following two actions: A. Send a questionnaire to the project participants and seek their feedback: The project manager should gather feedback from project participants to assess their satisfaction with the project. This can be done through a questionnaire or survey. Feedback is essential to identify areas of improvement and enhance future projects. D. Prepare the lessons learned from the project phase: The project manager should prepare a comprehensive document outlining the lessons learned from the project phase. This document should capture both the positive and negative aspects of the project. The lessons learned can help to improve project management processes and inform future projects
upvoted 2 times
JNLigonde
1 year, 5 months ago
The focus of the situation presented is to gather users’ feedback. You can only know which lessons you learned regarding the users after you have communicated with them, by looking at how that interaction was planned in the communications plan.
upvoted 1 times
...
...
Trytrio
1 year, 8 months ago
Selected Answer: AD
its A and D
upvoted 4 times
...
rajeshtk
2 years, 1 month ago
How could B the correct answer?
upvoted 1 times
[Removed]
2 years, 1 month ago
The communications management plan will likely have guidelines on how to communicate with your stakeholders, which in this case, is the end user they want feedback from. I'll give you an example, I see people use sites that allow for surveys, however in some countries, those same sites may be blocked, or you'll have users who don't know the policy and create one using a "free" account that has ads, etc. that may interfere with collecting feedback. The data and feedback might be sensitive information that shouldn't be posted with a publicly accessible link, there's plenty of reasons you want to refer to the guideline on how to communicate, which is why B is correct.
upvoted 10 times
aqz_111
1 year, 4 months ago
Communication management plan tell how to communication such as method (by email, phone etc) what information can be communicated and to who. The question is asking about satisfaction so it is 'evaluation'. I think lesson learned is telling what went well and what not well well. I select D
upvoted 1 times
...
rajeshtk
2 years ago
Agree on your thought. Thanks
upvoted 2 times
...
leo_gold
1 year, 10 months ago
I hear you! but don't you think D makes more sense than B as the lessons learned will have more context about the enduser experience?
upvoted 3 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago