A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
[Removed]
Highly Voted 2 years, 9 months ago23169fd
Most Recent 9 months, 2 weeks agoKim222
10 months, 1 week agoKim222
10 months, 1 week agosegatarasov
1 year, 4 months agojosephsafiran
1 year, 5 months agoatoms101
1 year, 6 months agoLucky_Cindy
1 year, 8 months agoestimater
1 year, 8 months agoOnly12go
1 year, 8 months agoFyrus
1 year, 8 months agokevzzz
1 year, 9 months agozayn_1983
1 year, 10 months agovictory108
1 year, 10 months agoSteAle
2 years agoThirukj
2 years agoAP2023S
2 years, 1 month agoemelba
2 years, 1 month ago