A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?
[Removed]
Highly Voted 2 years, 7 months ago23169fd
Most Recent 7 months, 1 week agoKim222
8 months agoKim222
8 months agosegatarasov
1 year, 2 months agojosephsafiran
1 year, 3 months agoatoms101
1 year, 4 months agoLucky_Cindy
1 year, 6 months agoestimater
1 year, 6 months agoOnly12go
1 year, 6 months agoFyrus
1 year, 6 months agokevzzz
1 year, 7 months agozayn_1983
1 year, 8 months agovictory108
1 year, 8 months agoSteAle
1 year, 10 months agoThirukj
1 year, 10 months agoAP2023S
1 year, 11 months agoemelba
1 year, 11 months ago