A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?
Dinesh1987
Highly Voted 2 years, 2 months agoAcumen88
1 year, 11 months agoJanek_94
2 months, 3 weeks agod2dc878
Most Recent 4 weeks, 1 day agoPrincessviv96
1 month agocheebooboo
1 month, 1 week agoAjitZavade
2 months, 1 week agoAjitZavade
2 months, 1 week agoChymKuBoy
2 months, 2 weeks agokavikris
5 months agoduy193193
7 months agoMgaidiwahid
7 months, 1 week agoLotToLearn
7 months, 1 week agoAmirov
7 months, 2 weeks agoPragati06
7 months, 2 weeks agoMsPigeon
11 months, 2 weeks agoakashushi007
11 months, 3 weeks agoompk
11 months, 3 weeks agoKhoiCX
11 months, 4 weeks ago