A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?
Dinesh1987
Highly Voted 2 years, 4 months agoAcumen88
2 years, 1 month agoJanek_94
5 months agoMsPigeon
Highly Voted 1 year, 1 month agoa3432e2
Most Recent 2 weeks, 6 days agoAnssoo
2 months agod2dc878
3 months agoPrincessviv96
3 months, 1 week agocheebooboo
3 months, 2 weeks agoAjitZavade
4 months, 1 week agoAjitZavade
4 months, 1 week agoChymKuBoy
4 months, 3 weeks agokavikris
7 months, 1 week agoduy193193
9 months, 1 week agoMgaidiwahid
9 months, 2 weeks agoLotToLearn
9 months, 2 weeks agoAmirov
9 months, 3 weeks agoPragati06
9 months, 3 weeks agoakashushi007
1 year, 1 month ago