Exam PMP topic 1 question 368 discussion

Actual exam question from PMI's PMP
Question #: 368
Topic #: 1
[All PMP Questions]

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI).
What should the project manager do?

  • A. Revisit the communications management plan and make necessary adjustments.
  • B. Revisit the scope management plan and note this as a risk.
  • C. Continue developing based on the project management plan and address the issue post delivery.
  • D. Schedule a meeting with the product owner and finance team to agree on course corrections.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 month ago
Selected Answer: D
not clear why do we need PO here for D
upvoted 1 times
...
Lucky_Cindy
6 months, 1 week ago
Selected Answer: D
D. Schedule a meeting with the product owner and finance team to agree on course corrections
upvoted 1 times
...
victory108
8 months, 2 weeks ago
Selected Answer: D
D. Schedule a meeting with the product owner and finance team to agree on course corrections
upvoted 1 times
...
RevZig67
1 year ago
Selected Answer: D
In this situation, the finance team's concerns need to be addressed to ensure that the project is financially feasible and can be approved. The project manager should schedule a meeting with the product owner and finance team to discuss the issue, understand the finance team's concerns, and work together to develop a solution that meets everyone's needs. This may involve revising the estimated ROI or making other adjustments to the project plan. It is important to address the issue as soon as possible to avoid any delays or potential project cancellations.
upvoted 2 times
...
Adala
1 year, 7 months ago
A is the correct answer
upvoted 2 times
[Removed]
1 year, 7 months ago
It is not, D is correct because the business case is presented in the project charter. The communications plan is developed after the charter, so revisiting it won't have any impact on the root cause of this issue. You would want to meet with them and get their input, which is the root cause.
upvoted 11 times
rajeshtk
1 year, 6 months ago
Agreed.
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago