A project manager is managing a project that has a new sponsor who is cutting the budget. As a servant leader, how should the project manager handle the budget cuts with the team?
A.
Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.
B.
Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan.
C.
Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope.
D.
Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Princessviv96
1 month, 1 week agobetterthanyesterday
5 months, 3 weeks agoNotImportant
5 months, 2 weeks agoBuviD
1 year, 4 months agoLhenica
1 year, 5 months agoGabMonterey
1 year, 5 months agoMuntadher
1 year, 9 months agovictory108
1 year, 11 months agoterryp
2 years, 2 months agoGanzee
2 years, 4 months agoNickybhai
2 years, 7 months agolgarciabr1
2 years, 3 months agomodsjunk
2 years, 7 months ago