Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards. What should the project manager do?
A.
Ask the senior manager to approve the user acceptance testing (UAT) plan
B.
Inform the senior manager that there are approved quality standards
C.
Review the quality management plan with the senior manager
First of all, this is an agile approach. In agile there are no project management plans. The most accurate way to check qualities agile approach is through sprint review from customers so C cannot be the answer
C. Review the quality management plan with the senior manager.
If a senior manager expresses concerns about the project meeting quality standards, it is important for the project manager to address these concerns promptly. Reviewing the quality management plan with the senior manager can help to identify any gaps in the plan that may be contributing to the concerns. This review can also help to ensure that the senior manager is aware of the quality standards and the project's approach to meeting those standards.
Asking the senior manager to approve the user acceptance testing (UAT) plan (option A) may not address the concerns about overall project quality. Similarly, simply informing the senior manager that there are approved quality standards (option B) may not provide enough detail to address the specific concerns. Estimating backlog items to forecast quality (option D) may be useful, but it should not be the primary response to a senior manager's concerns about project quality.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Drwaleed
Highly Voted 1 year, 6 months agojiljap
Most Recent 1 week agod482858
2 weeks, 6 days agoBruce_Liu
4 months, 1 week agoGabMonterey
5 months agoMamoonpk
5 months, 1 week agoSerMak
6 months, 2 weeks agoLucky_Cindy
6 months, 3 weeks agoTuanit
6 months, 3 weeks agoSonya_123
7 months, 1 week agoGoku_PMP
8 months, 3 weeks agoAsakthi
8 months, 3 weeks agoMuntadher
9 months, 2 weeks agosmartrammy
10 months agovictory108
11 months agoJMCCRAY
1 year agoHin915
1 year ago