Question #: 441
Topic #: 1
[All PMP Questions]

A company starts implementing Scrum. About halfway through the first sprint, communication issues develop. Some project team members are not in sync with other team members.
What is the cause for this communication gap?

  • A. The project sprint board has not been updated
  • B. Daily standup meetings were not held or enforced
  • C. The project status dashboard has not been updated
  • D. The communications management plan has not been developed
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Proctored_Expert
Highly Voted 1 year, 4 months ago
Selected Answer: B
The cause for the communication gap in this situation is likely that daily standup meetings were not held or enforced (option B). In Scrum, a sprint is a time-boxed iteration of work during which a specific set of tasks is completed and delivered. During a sprint, daily standup meetings, also known as daily Scrums, are held to provide an opportunity for team members to communicate with each other and coordinate their work. The purpose of daily standup meetings is to ensure that team members are aware of what each other is working on, identify any issues or obstacles that need to be addressed, and coordinate their efforts to ensure that the tasks for the sprint are completed on time. If daily standup meetings are not held or enforced, it can lead to a communication gap and a lack of coordination among team members, which can negatively impact the progress and success of the sprint.
upvoted 10 times
...
4f6ae44
Most Recent 1 week, 6 days ago
this is joke. The answer is for sure B and not sure how A is correct!!!
upvoted 1 times
...
Bruce_Liu
3 months, 1 week ago
Selected Answer: B
B is most direct answer.
upvoted 1 times
...
Mohammad707
4 months ago
Selected Answer: B
The cause for the communication gap in this situation is likely that daily standup meetings were not held or enforced
upvoted 1 times
...
Psadon
4 months, 2 weeks ago
Selected Answer: B
B. Daily standup meetings were not held or enforced. The daily standup meetings, also known as Daily Scrum, are a key component of Scrum methodology. These short, daily meetings provide an opportunity for team members to synchronize, discuss progress, and identify any obstacles. If these meetings are not held or enforced, it can lead to communication issues and a lack of synchronization among team members
upvoted 1 times
...
odylec
4 months, 2 weeks ago
Selected Answer: D
right is D. you cant enforce something
upvoted 1 times
...
Only12go
6 months, 2 weeks ago
Selected Answer: B
B. Daily standup meetings were not held or enforced. In Scrum, daily standup meetings (also known as daily scrum meetings or daily stand-ups) are a crucial part of the framework. These meetings are designed to provide a daily opportunity for team members to synchronize, share updates, and identify any impediments or blockers. When daily standup meetings are not held or enforced, it can lead to communication gaps and a lack of synchronization among team members. This can result in team members not being aware of each other's progress or challenges, which can impact the overall progress of the sprint and project.
upvoted 1 times
...
victory108
8 months, 1 week ago
Selected Answer: B
B. Daily standup meetings were not held or enforced
upvoted 1 times
...
kevzzz
8 months, 4 weeks ago
Selected Answer: A
A sprint board is a visual representation of the work to be done in a single sprint. The sprint board allows the Scrum team to: Identify the tasks that need to be completed. Ensure that everyone is working on a project task. Keep track of the progress of an active sprint. If the board isn't updated, the team is then our of sync, the project sprint fails.
upvoted 1 times
...
AMikhailovskiy
9 months, 3 weeks ago
The answer is A, because "Some project team members are not in sync with other team members." It means that the project sprint board (scrum board) has not been updated
upvoted 1 times
...
TheAWSGuru
1 year, 4 months ago
Selected Answer: B
B is the right answer
upvoted 2 times
...
KA90
1 year, 5 months ago
Selected Answer: B
I think B is correct
upvoted 2 times
...
lannt307
1 year, 5 months ago
Selected Answer: A
I think A is correct. Because, Daily standup meetings were enforced, if the project sprint board (scrum board) has not been updated then still missing information in sync with other team members.
upvoted 2 times
aqz_111
10 months, 2 weeks ago
Thanks, i only know information radiator and did not know it is also called sprint board or scrum board. yes, the answer should be A
upvoted 1 times
...
...
Alphasham
1 year, 6 months ago
Selected Answer: B
B is correct.
upvoted 1 times
...
Franco11
1 year, 6 months ago
Selected Answer: A
Answer is Correct as the information Radiator is always updated and is used in scrum
upvoted 1 times
...
[Removed]
1 year, 7 months ago
Selected Answer: B
Sprint board usually would stay the same and wouldn't need updating until the end of the iteration, so I'm going to go with B.
upvoted 2 times
...
guyver0523
1 year, 7 months ago
Selected Answer: B
why not B?
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...