Actual exam question from PMI's PMP
Question #: 348
Topic #: 1
[All PMP Questions]

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?

  • A. Inform the project sponsor of the stakeholder's dissatisfaction.
  • B. Review the requirements traceability matrix and conduct inspections.
  • C. Document the issue in the issue log and send a report to management.
  • D. Notify the stakeholder that arbitration procedures will be followed.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: B
B. Review the requirements traceability matrix and conduct inspections
upvoted 1 times
...
Only12go
7 months ago
Selected Answer: B
Once the project manager has reviewed the traceability matrix and conducted inspections, they can better understand whether there are valid concerns about the deliverables' quality. Depending on the findings, further actions can be taken, such as initiating corrective actions, addressing any discrepancies, or engaging in discussions with the stakeholder to resolve their concerns. Additionally, documenting these findings and actions in the issue log is a good practice to maintain transparency and accountability.
upvoted 2 times
...
Fyrus
7 months, 2 weeks ago
Selected Answer: B
B seems more reasonable. C seems like you just want to pass to problem forward.
upvoted 1 times
...
kevzzz
8 months ago
Selected Answer: B
A traceability matrix is a document that details the technical requirements for a given test scenario and its current state. It helps the testing team understand the level of testing that is done for a given product. The stakeholder is questioning the technical requirements, so review that document FIRST, then address.
upvoted 2 times
...
kayyaly
8 months, 3 weeks ago
Selected Answer: B
my answer is B, C option is only to report the issue with management, no action is taken
upvoted 1 times
...
victory108
9 months, 1 week ago
Selected Answer: B
B. Review the requirements traceability matrix and conduct inspections
upvoted 1 times
...
SteAle
10 months, 3 weeks ago
Selected Answer: B
Before taking any issues up with the management, a PM needs to find out the root cause. If you read the question carefully, it's not the deliverables that were not accepted, but the quality specifications. So, it is worth conducting an inspection to understand what is wrong
upvoted 1 times
SteAle
10 months, 3 weeks ago
PMBOK 6: "Inspection includes activities such as measuring, examining, and validating to determine whether work and deliverables meet requirements and product acceptance criteria."
upvoted 1 times
...
...
abdelilahfa
11 months, 2 weeks ago
Selected Answer: C
The quality specifications and deliverables have already been formally accepted
upvoted 1 times
...
JYKL88
1 year, 1 month ago
Will go with B
upvoted 1 times
...
Trytrio
1 year, 2 months ago
I would have said B
upvoted 2 times
...
[Removed]
1 year, 8 months ago
Selected Answer: C
I think this is C because the quality specifications and deliverables have already been formally accepted, so I don't think it can be B. You wouldn't do an inspection after your deliverables have been accepted, unless the customer as a whole comes back to you and has an issue. It is not uncommon to find a stakeholder complaining about contracted work.
upvoted 3 times
Franco11
1 year, 7 months ago
True, the deliverables are validated so no need for the RTM
upvoted 1 times
...
rajeshtk
1 year, 7 months ago
What would the management do here? Shouldn't the PM do some analysis and see where it went wrong if it had gone wrong?
upvoted 2 times
pmp_237student
1 year, 4 months ago
Your deliverables have been formally accepted already meaning due processes where followed.
upvoted 1 times
Maccaoidh
1 year, 1 month ago
Maybe I am reading the question wrong, but only " The quality specifications for the project deliverables are formally accepted." Nothing says that the actual deliverables were formally accepted. I went with B.
upvoted 4 times
...
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...