A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
Lucky_Cindy
6 months, 3 weeks agoOnly12go
7 months agoFyrus
7 months, 2 weeks agokevzzz
8 months agokayyaly
8 months, 3 weeks agovictory108
9 months, 1 week agoSteAle
10 months, 3 weeks agoSteAle
10 months, 3 weeks agoabdelilahfa
11 months, 2 weeks agoJYKL88
1 year, 1 month agoTrytrio
1 year, 2 months ago[Removed]
1 year, 8 months agoFranco11
1 year, 7 months agorajeshtk
1 year, 7 months agopmp_237student
1 year, 4 months agoMaccaoidh
1 year, 1 month ago