The city has decided to build a new tram station. The project will include various approaches. The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle. Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action.
What two actions should the project manager take'? (Choose two.)
modsjunk
Highly Voted 2 years, 7 months agoJamrock
2 years agoAnne99
Most Recent 4 months, 1 week agovlxx
7 months, 3 weeks agoNgho
10 months, 1 week agoKim222
11 months, 2 weeks agoBruce_Liu
1 year, 5 months agod370e49
11 months agod370e49
11 months agoced45c8
1 year, 7 months agoOnly12go
1 year, 9 months agovictory108
1 year, 11 months agoAish_
2 years agokevzzz
2 years agoDawn6699
2 years, 2 months agoJYKL88
2 years, 4 months agoWeslineo
2 years, 5 months agoPMPStudent
2 years, 8 months agongocnb1
2 years, 8 months ago[Removed]
2 years, 10 months agoPaulpeng
2 years, 10 months agoBalaraju
2 years, 10 months agorajeshtk
2 years, 9 months ago