During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion. What should the project manager do next?
A.
Discuss this issue with the project sponsor to request additional funding to implement mitigation
B.
Prequalify contractors with proven track records to eliminate productivity concerns
C.
Add construction productivity to the risk register and develop a mitigation strategy for site execution
D.
Hire a construction management consultant to develop a comprehensive site execution plan
The learning from prior project was about construction productivity. So in order to prevent it happen in a new project, it has to monitored with a mitigation plan. Correct answer is C
upvoted 2 times
...
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Princessviv96
1 month agomesacgon
6 months, 1 week agoTuanit
7 months agoAsakthi
9 months agoMuntadher
9 months, 2 weeks agovictory108
11 months, 2 weeks agoMobarak7
1 year agoSandiago
1 year, 6 months agolongge
1 year, 6 months agoFranco11
1 year, 7 months agorajeshtk
1 year, 6 months ago