During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?

  • A. Discuss this issue with the project sponsor to request additional funding to implement mitigation
  • B. Prequalify contractors with proven track records to eliminate productivity concerns
  • C. Add construction productivity to the risk register and develop a mitigation strategy for site execution
  • D. Hire a construction management consultant to develop a comprehensive site execution plan
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
1 month ago
Selected Answer: C
Add the potential risk to the risk register and then find ways to mitigate the risk so it doesn't affect the overall site execution
upvoted 1 times
...
mesacgon
6 months, 1 week ago
LA respuesta es C. Desde la planificación ya se inicia con la identificación de riesgos.
upvoted 1 times
...
Tuanit
7 months ago
Selected Answer: B
I would take actions on B first then add actions on C for the later.
upvoted 1 times
...
Asakthi
9 months ago
C ..add to the risk register
upvoted 1 times
...
Muntadher
9 months, 2 weeks ago
Selected Answer: C
i think C is most fit
upvoted 2 times
...
victory108
11 months, 2 weeks ago
Selected Answer: C
C. Add construction productivity to the risk register and develop a mitigation strategy for site execution
upvoted 1 times
...
Mobarak7
1 year ago
Selected Answer: C
C is the right choice
upvoted 2 times
...
Sandiago
1 year, 6 months ago
Selected Answer: C
C is correct, Identifying and mitigating the risk
upvoted 2 times
...
longge
1 year, 6 months ago
Selected Answer: C
it is C
upvoted 1 times
...
Franco11
1 year, 7 months ago
Selected Answer: B
The project is in Initiation phase, and the risk register is not yet created
upvoted 2 times
rajeshtk
1 year, 6 months ago
The learning from prior project was about construction productivity. So in order to prevent it happen in a new project, it has to monitored with a mitigation plan. Correct answer is C
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago