Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 38 discussion

Actual exam question from PMI's PMP
Question #: 38
Topic #: 1
[All PMP Questions]

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?

  • A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule
  • B. Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project
  • C. Push out the project timeline according to the vacation plan in place based on the recent company policy
  • D. Discuss the vacation plan and include scheduling changes in the change log database
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
achacyrille
Highly Voted 1 year, 2 months ago
Selected Answer: D
Notice it didn't say all workers will go on vacation the same day or period. It simply says before the year ends. The PM in the Schedule Management during the Develope Schedule Process considers as an input the Resource Managment Plan during Aquire/allocate Resource Process developed with the help of the functional manager incharge of the resources and which usually takes into consideration such scenarios. The Vacation plan is thus discused and shedule replanned accordingly. Normally this is achieved through lags placed on activities.
upvoted 11 times
...
Bhanu2086
Most Recent 1 week, 5 days ago
Selected Answer: A
There is a risk of schedule getting extended due to organisational announcement. So as a PM we need to come up with a risk mitigation plan rather than straightaway accomodating the schedule changes. Hence, we need to discuss with the team and come up with a plan to minimize the impact on the project schedule.
upvoted 1 times
...
hoomz
2 months, 3 weeks ago
Selected Answer: A
D may not be the most proactive approach compare to A
upvoted 2 times
...
kraze29
3 months, 3 weeks ago
Selected Answer: A
I think option A is more appropriate. If it's affecting the project timeline then before its included, need to be assure that it will have minimal impact.
upvoted 2 times
...
josephsafiran
4 months ago
Selected Answer: A
I think A is the Answer Because in D if we want to update the Change Log, we need to have approval from the Board, and I know it's the company's decision and they will approve it but in some cases, the answer should mention about requesting changes Always need to communicate with the team and FM without changing things and if that doesn't give us a solution we will do the D
upvoted 1 times
...
BuviD
4 months ago
Selected Answer: A
A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule
upvoted 2 times
...
mmhawish
4 months, 1 week ago
Selected Answer: A
(option D) is a reactive approach and may not be effective in minimizing the impact of the vacation time on the project schedule.
upvoted 1 times
...
KIM6945
5 months, 1 week ago
Selected Answer: A
ANSWER A
upvoted 1 times
...
Farooqsm
5 months, 3 weeks ago
Question says the vacation plan may cause a change in the project time line and did not say will cause a change. So answer is D
upvoted 1 times
...
Tuanit
7 months ago
Selected Answer: D
D Change Request is needed
upvoted 1 times
...
Exp11
7 months, 2 weeks ago
Selected Answer: A
Vacation time is already requested. Hence schedule changes are required. Correct ans should be D
upvoted 2 times
...
Pranav2204
7 months, 2 weeks ago
Selected Answer: D
D is the ans
upvoted 1 times
...
Nelsned
8 months ago
Leaving project management techniques aside A & D both sound correct but A is more elaborate, D is vague.
upvoted 2 times
...
TienHa
8 months, 3 weeks ago
Selected Answer: D
D includes A that already discuss a plan with team and have a change with the minor impact.
upvoted 1 times
...
Chrisaytunes
9 months, 4 weeks ago
Selected Answer: A
The most appropriate action for the project manager to address the situation would be A: Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule. Communicating and collaborating with both functional management and the project team is essential in determining a vacation schedule that has the least impact on the project timeline.
upvoted 3 times
...
smartrammy
10 months, 1 week ago
Selected Answer: A
A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule
upvoted 3 times
...
SteAle
10 months, 2 weeks ago
Selected Answer: A
A. First step should be always to assess the impact on the project constraints.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...