Actual exam question from PMI's PMP
Question #: 363
Topic #: 1
[All PMP Questions]

In a software development project, the product owner and development team agree on a sprint backlog. The highest priority in the backlog is to build a payment module. The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?

  • A. Let the developers focus on the refactoring work and discuss it in the retrospective.
  • B. Restate to the developers the importance of focusing and meeting the sprint goal.
  • C. Escalate the issue to the developers' functional managers.
  • D. Praise the developers for their proactivity and focus on quality.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
FlorinaP
Highly Voted 1 year, 11 months ago
Selected Answer: B
the technical debt can be prioritized next
upvoted 9 times
...
josephsafiran
Most Recent 1 year ago
Selected Answer: B
The project manager should choose option B. Restate to the developers the importance of focusing and meeting the sprint goal. In Scrum, the sprint goal is a commitment made by the development team, and it’s crucial to focus on the agreed-upon work to achieve this goal. While it’s important to address technical debt and potential issues, these should ideally be planned for and included in the sprint backlog during the sprint planning meeting. If the refactoring is critical, it could be discussed with the product owner and potentially included in a future sprint. Remember, the key to successful Scrum is transparency, inspection, and adaptation.
upvoted 2 times
...
Ngcy2023
1 year, 1 month ago
i think shiuld be A, because spring shoukd empower team to make decision and trust them can done their work?
upvoted 1 times
...
Lucky_Cindy
1 year, 2 months ago
Selected Answer: B
B. Restate to the developers the importance of focusing and meeting the sprint goal
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: B
B. Restate to the developers the importance of focusing and meeting the sprint goal
upvoted 1 times
...
Drogbadrog
1 year, 10 months ago
Sprints are done based on pioritization
upvoted 1 times
...
Riro2
1 year, 11 months ago
Selected Answer: A
Right answer is A. Refactoring job must be done in order to avoid future issues, the remaining work not achieved during this sprint will be reported to next sprints.
upvoted 2 times
AstridN
1 year, 6 months ago
I thought but then read it might ...it's a risk..didn't occur yet
upvoted 1 times
...
...
Bobbie30
2 years, 1 month ago
I will go for B because sprints cannot be changed halfway
upvoted 2 times
...
guyver0523
2 years, 3 months ago
why not A?
upvoted 1 times
rajeshtk
2 years, 3 months ago
In a sprint, the objective is to achieve the goal
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...