A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.
How should the project manager address this situation?
Desmonddoyin
Highly Voted 2 years, 1 month agoHashi1_snr
1 year, 9 months agoNayla87
Most Recent 3 months, 1 week agoPrincessviv96
4 months, 2 weeks agolatigo
5 months agoCG1111
6 months, 3 weeks agoDeepakuc
9 months, 1 week agoBuviD
1 year, 7 months agoKalhan06
1 year, 8 months agoGabMonterey
1 year, 8 months agoJames_Wild
1 year, 8 months agoMuntadher
2 years agoHoraceZzzz
2 years agovictory108
2 years, 3 months agoBenPappoe
2 years, 3 months agoAnna12675
2 years, 3 months agoHungdv
2 years, 5 months agoHung1
2 years, 4 months agoachacyrille
2 years, 5 months ago