A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
Aish_
Highly Voted 2 years agoJAQM
Most Recent 4 months, 1 week agoPrincessviv96
4 months, 3 weeks agoTerryV01
6 months, 1 week agoengamin
6 months, 1 week agoFauziYusmin
7 months, 2 weeks agottkong168
8 months, 1 week agocrypto_dreams_medellin
9 months, 1 week agofragar65
10 months, 2 weeks agoLotToLearn
10 months, 3 weeks agoziyaetuk
10 months, 4 weeks agoJMCCRAY
10 months, 4 weeks agoOnly12go
10 months, 4 weeks agodjgdgaf
10 months, 4 weeks agoPragati06
11 months agoTaha1981
11 months agoAnhHN11
1 year, 1 month ago