A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of the team members were stressed due to over commitments.
What should the project manager do?
longge
Highly Voted 1 year, 11 months agoPaulPMP
1 year, 6 months agoPrincessviv96
Most Recent 4 weeks, 1 day agoductrinh
1 month, 2 weeks agoK91
3 months, 2 weeks agoDeemmoh
3 months, 2 weeks agoWakeupsid
3 months, 4 weeks agoAbefroeman
7 months, 1 week agomdkhassan
7 months, 2 weeks ago58e5964
9 months, 2 weeks agoTOLANTONGO
7 months, 2 weeks agoodylec
9 months, 2 weeks agoTuanit
1 year agonemm235
1 year, 1 month agoMuntadher
1 year, 3 months agoMuntadher
1 year, 3 months agoSteAle
1 year, 4 months agovictory108
1 year, 5 months agocwilson91
1 year, 5 months agoAP2023S
1 year, 5 months ago