exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 63 discussion

Actual exam question from PMI's PMP
Question #: 63
Topic #: 1
[All PMP Questions]

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two.)

  • A. Provide training to the team on emotional intelligence and status reporting techniques
  • B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders
  • C. Share weekly status reports with detailed information about the project and team performance
  • D. Submit performance reports and task assignments to keep the stakeholder informed
  • E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback
Show Suggested Answer Hide Answer
Suggested Answer: BE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
zul_n
Highly Voted 2 years, 5 months ago
Selected Answer: BE
A. Provide training to the team on emotional intelligence and status reporting techniques - PM delivers status report, not the team members B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders - make sense building relationship with the stakeholders C. Share weekly status reports with detailed information about the project and team performance - won't help building relationsahip with the stakeholders D. Submit performance reports and task assignments to keep the stakeholder informed - won't help building relationsahip with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback - make sense building relationship with the stakeholders
upvoted 7 times
...
Princessviv96
Most Recent 1 month, 1 week ago
Selected Answer: BE
B&E are the best options to improve stakeholder communication in this scenario
upvoted 1 times
...
Paramak
9 months, 3 weeks ago
Selected Answer: BE
Promote a transparent environment for the team and schedule regular meetings with stakeholder and get their feedback. Both promotes Agile methodology.
upvoted 1 times
...
BuviD
1 year, 4 months ago
Selected Answer: CE
E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback and C
upvoted 1 times
...
stujam
1 year, 9 months ago
B & E.
upvoted 1 times
...
Asakthi
1 year, 9 months ago
B and E
upvoted 1 times
...
Muntadher
1 year, 9 months ago
Selected Answer: BE
most applicable choice B and E
upvoted 1 times
...
AH1007
1 year, 11 months ago
Selected Answer: BE
B and E are suitable for this situation.
upvoted 1 times
...
Red_Apple1
1 year, 11 months ago
Selected Answer: BE
i thick B & E
upvoted 1 times
...
victory108
1 year, 11 months ago
Selected Answer: BE
B. Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders E. Schedule regular meetings with the key stakeholder to provide updates and receive feedback
upvoted 1 times
...
sanjeevjha
2 years, 3 months ago
B & E is correct option
upvoted 1 times
...
viethunggen
2 years, 4 months ago
Selected Answer: BE
BE is correct
upvoted 1 times
...
Ganzee
2 years, 4 months ago
B AND E
upvoted 1 times
...
PMPStudent
2 years, 4 months ago
B and E are correct
upvoted 1 times
...
longge
2 years, 6 months ago
Selected Answer: BE
focus on communication
upvoted 3 times
...
rajeshtk
2 years, 7 months ago
Isn't it A&B the correct answer?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago