A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two.)
zul_n
Highly Voted 2 years, 5 months agoPrincessviv96
Most Recent 1 month, 1 week agoParamak
9 months, 3 weeks agoBuviD
1 year, 4 months agostujam
1 year, 9 months agoAsakthi
1 year, 9 months agoMuntadher
1 year, 9 months agoAH1007
1 year, 11 months agoRed_Apple1
1 year, 11 months agovictory108
1 year, 11 months agosanjeevjha
2 years, 3 months agoviethunggen
2 years, 4 months agoGanzee
2 years, 4 months agoPMPStudent
2 years, 4 months agolongge
2 years, 6 months agorajeshtk
2 years, 7 months ago