A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not available and the review is often delayed, which results in increased rework for the team.
What should the project manager do?
Aish_
Highly Voted 2 years agoJAQM
Most Recent 4 months, 1 week agoPrincessviv96
4 months, 3 weeks agoGracemade
5 months, 3 weeks agoengamin
6 months, 1 week agoFauziYusmin
7 months, 2 weeks agottkong168
8 months, 1 week agoMalikSaab
8 months, 2 weeks agocrypto_dreams_medellin
9 months, 1 week agocrypto_dreams_medellin
9 months, 2 weeks agoPragati06
11 months agoTaha1981
11 months agoAditech
1 year, 4 months agoberouz
1 year, 4 months ago09e9f80
1 year, 5 months agoBuviD
1 year, 7 months agokhloreeen
1 year, 8 months ago