A project schedule risk has turned into an issue. The project manager foresees delays in project execution.
What should the project manager do to resolve the issue?

  • A. Escalate the issue to senior leadership for resolution
  • B. Work with relevant stakeholders to determine possible solutions
  • C. Update the schedule baseline to the new project time line
  • D. Update the risk management plan and send it to the project team
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
d2dc878
3 weeks, 2 days ago
Selected Answer: B
B Not D becausePurpose: The primary goal of a risk management plan is to proactively address potential problems or uncertainties that could impact a project's success or an organization's operations. Key Elements: Risk Identification: Identifying potential risks, both positive and negative, that could affect the project or organization. Risk Assessment: Evaluating the likelihood and potential impact of each identified risk. Risk Response Planning: Developing strategies to address the identified risks, including mitigation, avoidance, transfer, or acceptance. Risk Monitoring and Control: Continuously monitoring the risks and implementing controls to ensure the effectiveness of the risk management plan.
upvoted 1 times
...
Princessviv96
3 weeks, 5 days ago
Selected Answer: B
In may opinion , the PM should work with the relevant stakeholders to see what possible solution will be and if all else fails he can escalate
upvoted 1 times
...
K91
3 months, 2 weeks ago
Selected Answer: B
If D says "Review risk register, and implement the risk response", it's hard to choose B or D.
upvoted 1 times
...
Tuanit
6 months, 3 weeks ago
Selected Answer: B
B work with relevant stakeholders first.
upvoted 1 times
...
SteAle
10 months, 1 week ago
Selected Answer: B
B. it is too late to update the risk management plan as the project has run into an issue. when a risk becomes an issue, the first step should be to work out possible solutions.
upvoted 2 times
...
Yuxiao
11 months ago
D is absolutely wrong since it is no longer be a risk but an issue, so you cannot log it into risk management plan (also you can log risk into risk register, not risk management plan), so B
upvoted 4 times
...
victory108
11 months, 1 week ago
Selected Answer: B
B. Work with relevant stakeholders to determine possible solutions
upvoted 2 times
...
ad_27
1 year, 2 months ago
Selected Answer: A
it says it turned into an issue already, so it needs to be escalated.
upvoted 1 times
...
pmp_237student
1 year, 4 months ago
As a project manager your first response to any issue is to find a work around. Escalation is only a secondary response so I go with B
upvoted 2 times
...
PMPStudent
1 year, 4 months ago
The Correct answer is B.
upvoted 2 times
...
arnibert
1 year, 5 months ago
Selected Answer: B
B seems correct to me because I would first work with relevant stakeholders to determine possible solutions and only then escalate (A) if needed
upvoted 1 times
...
kamdev
1 year, 6 months ago
Its was Risk hence there should be a response plan already, which must have discussed with stakeholders for response , but seem it did not work and turn in to issue . So this needs to be escalated to next level I go with A
upvoted 4 times
...
longge
1 year, 6 months ago
Selected Answer: D
why not D???
upvoted 2 times
TestWater
1 year, 1 month ago
risk management plan --- not the registry
upvoted 2 times
...
Franco11
1 year, 6 months ago
U should communicate the identified risk with the relevant stakeholder and apply the risk risponse
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago