exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 513 discussion

Actual exam question from PMI's PMP
Question #: 513
Topic #: 1
[All PMP Questions]

A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?

  • A. Hold a stakeholder meeting to align timelines and scope expectations
  • B. Crash the schedule to shorten the timeline while keeping the scope unchanged
  • C. Update the cost management plan to allocate more resources to the project to finish the scope earlier
  • D. Reduce the scope of the project by removing activities and shortening the timeline
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
Highly Voted 2 years, 7 months ago
Selected Answer: A
A. Hold a stakeholder meeting to align timelines and scope expectations
upvoted 5 times
...
DavidTri
Most Recent 10 months, 2 weeks ago
vote A, need to get approval before make the change
upvoted 1 times
...
kevindebruyne
1 year, 9 months ago
Selected Answer: A
A first then can based on the result to decide the next action. After A can be B or C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...