A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date. What should the project manager do?
A.
Hold a stakeholder meeting to align timelines and scope expectations
B.
Crash the schedule to shorten the timeline while keeping the scope unchanged
C.
Update the cost management plan to allocate more resources to the project to finish the scope earlier
D.
Reduce the scope of the project by removing activities and shortening the timeline
A first then can based on the result to decide the next action. After A can be B or C
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
Highly Voted 2 years, 7 months agoDavidTri
Most Recent 10 months, 2 weeks agokevindebruyne
1 year, 9 months ago