A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials.
What should the project manager do next?
Anne99
4 weeks, 1 day agoJerryMag4
1 month, 1 week agoea4e1f8
8 months, 1 week agoDavidTri
10 months agoBruce_Liu
1 year, 2 months agojosephsafiran
1 year, 3 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agoDavid983
1 year, 6 months agoAish_
1 year, 8 months agoAish_
1 year, 8 months agoSynikalDemon
1 year, 9 months agoAbbasTaki
1 year, 10 months agoEC123
1 year, 11 months agoadingmaki
1 year, 6 months agoFaozi
1 year, 11 months agoFiona1212
1 year, 11 months agoemelba
1 year, 11 months agoRevZig67
2 years ago