exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 200 discussion

Actual exam question from PMI's PMP
Question #: 200
Topic #: 1
[All PMP Questions]

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started working at the company. In the first meeting with the project manager, the director demands a weekly project status report.
What should the project manager do?

  • A. Invite the director to attend the daily standup meetings.
  • B. Share this with the team and ask them to develop reports for the director.
  • C. Introduce the agile aspect to the director and agree on a solution.
  • D. Explain to the director that agile projects have live reports.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PhongDang_PM
Highly Voted 8 months, 2 weeks ago
Selected Answer: D
D can someone explain why D is not an option, since Agile is transparency and the report is always available for anyone?
upvoted 5 times
K91
5 months, 1 week ago
D is a one-directional approach. The PM only explains how agile works, but doesn't listen to the person.
upvoted 2 times
...
...
maferosas
Most Recent 2 months, 2 weeks ago
Selected Answer: C
segun la IA ES La por lo siguiente: C. Presentar el aspecto ágil al director y acordar una solución. Esta opción refleja el enfoque más equilibrado y profesional. El director del proyecto: Educa al nuevo director sobre cómo funciona la gestión ágil. Reconoce la necesidad de información del nuevo director. Colabora para encontrar una solución que funcione para ambos, como informes ligeros basados en los artefactos ágiles ya existentes (burndown charts, tableros Kanban, etc.).
upvoted 1 times
...
krispara
6 months, 3 weeks ago
Selected Answer: C
providing education on agile is core here.
upvoted 1 times
...
Asakthi
1 year, 11 months ago
C. Introduce the agile aspect to the director and agree on a solution.
upvoted 1 times
...
victory108
2 years, 1 month ago
Selected Answer: C
C. Introduce the agile aspect to the director and agree on a solution
upvoted 1 times
...
Trytrio
2 years, 4 months ago
Selected Answer: C
Answer A can be an outcome of C. C is more general and to be chosen.
upvoted 3 times
...
arnibert
2 years, 7 months ago
Selected Answer: C
(A) violates the agile scrum definition for daily stand-ups
upvoted 1 times
...
faramade
2 years, 8 months ago
A is the Answer
upvoted 2 times
nyaopoko
2 years, 8 months ago
On other sites, the conclusion is C. We have to agree.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...