A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?
joesatriani
Highly Voted 2 years, 6 months agoTuanit
Highly Voted 1 year, 7 months agoPrincessviv96
Most Recent 1 month, 1 week agoductrinh
1 month, 2 weeks agoDeepakuc
5 months, 3 weeks agoAish_
7 months, 2 weeks agoKaran1102
1 year agoBuviD
1 year, 4 months agoMamoonpk
1 year, 5 months agoadingmaki
1 year, 6 months agoadingmaki
1 year, 6 months agoAlphy07
1 year, 8 months agokayyaly
1 year, 8 months agoziyaetuk
1 year, 9 months agoompk
1 year, 10 months agodjgdgaf
1 year, 2 months agoSteAle
1 year, 10 months agovictory108
1 year, 12 months ago