A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?
joesatriani
Highly Voted 2 years, 8 months agoTuanit
Highly Voted 1 year, 8 months agoNayla87
Most Recent 1 month, 3 weeks agoPrincessviv96
3 months agoductrinh
3 months, 1 week agoDeepakuc
7 months, 3 weeks agoAish_
9 months, 1 week agoKaran1102
1 year, 2 months agoBuviD
1 year, 5 months agoMamoonpk
1 year, 7 months agoadingmaki
1 year, 8 months agoadingmaki
1 year, 8 months agoAlphy07
1 year, 10 months agokayyaly
1 year, 10 months agoziyaetuk
1 year, 11 months agoompk
1 year, 12 months agodjgdgaf
1 year, 4 months agoSteAle
2 years ago