A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?
joesatriani
Highly Voted 2 years, 10 months agoTuanit
Highly Voted 1 year, 10 months agossokratess
Most Recent 3 weeks, 2 days agoNayla87
3 months, 1 week agoPrincessviv96
4 months, 3 weeks agoductrinh
4 months, 4 weeks agoDeepakuc
9 months, 1 week agoAish_
10 months, 4 weeks agoKaran1102
1 year, 4 months agoBuviD
1 year, 7 months agoMamoonpk
1 year, 8 months agoadingmaki
1 year, 10 months agoadingmaki
1 year, 10 months agoAlphy07
1 year, 11 months agokayyaly
1 year, 11 months agoziyaetuk
2 years, 1 month agoompk
2 years, 1 month agodjgdgaf
1 year, 5 months ago