A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After 3 days of work, the project manager completed two actions and spent US$80,000.
What should the project manager do next?
hussamali
Highly Voted 1 year, 9 months agojoesatriani
Highly Voted 2 years, 2 months agoJamrock
1 year, 6 months agohrson81
Most Recent 5 months, 2 weeks agoK91
6 months, 2 weeks agobuvana
9 months, 3 weeks agoBuviD
1 year agoGabMonterey
1 year, 1 month agoIvana_1701
1 year, 4 months agoAsakthi
1 year, 5 months agoSteAle
1 year, 6 months agovictory108
1 year, 8 months agoEC123
1 year, 8 months agoAnna12675
1 year, 8 months agoAP2023S
1 year, 8 months agoFaozi
1 year, 8 months agoFaozi
1 year, 8 months agoFaozi
1 year, 8 months agoKuzi
1 year, 9 months ago