A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
rajeshtk
Highly Voted 2 years, 8 months agoKim222
10 months agoAmitBI
1 year, 9 months agowittycroc
Most Recent 3 months, 3 weeks agoshpunk
4 months agoKim222
10 months agotonybuivannghia
11 months, 1 week agoc8ee0e6
11 months, 2 weeks agoBruce_Liu
1 year, 5 months agojosephsafiran
1 year, 5 months agohuynq185
1 year, 7 months agoLucky_Cindy
1 year, 8 months ago[Removed]
1 year, 8 months agoOnly12go
1 year, 8 months agokevzzz
1 year, 8 months agovictory108
1 year, 10 months agoAsakthi
1 year, 10 months agoOrochi
2 years agosuflam3
2 years, 1 month ago