A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan.
The project manager starts to present the budget but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
JYKL88
Highly Voted 2 years, 3 months agocwilson91
2 years, 1 month agoDavid983
1 year, 10 months agoPMPStudent
Highly Voted 2 years, 7 months ago21d5982
Most Recent 2 months, 3 weeks agoSuldan
3 months, 3 weeks agoljz
5 months, 1 week ago462729f
5 months, 2 weeks agoKim222
11 months, 2 weeks agoKennyMuffins
1 year, 6 months agojosephsafiran
1 year, 6 months agoxcjxcj
1 year, 8 months agovictory108
1 year, 11 months agoPaulPMP
2 years, 4 months agoFranco11
2 years, 9 months ago