A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan.
The project manager starts to present the budget but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
JYKL88
Highly Voted 2 years, 1 month agocwilson91
1 year, 11 months agoDavid983
1 year, 8 months ago21d5982
Most Recent 1 month, 1 week agoSuldan
2 months agoljz
3 months, 3 weeks ago462729f
3 months, 3 weeks agoKim222
9 months, 4 weeks agoKennyMuffins
1 year, 4 months agojosephsafiran
1 year, 4 months agoxcjxcj
1 year, 6 months ago[Removed]
1 year, 7 months agovictory108
1 year, 9 months agoPaulPMP
2 years, 3 months agoPMPStudent
2 years, 6 months agoFranco11
2 years, 8 months ago