A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan.
The project manager starts to present the budget but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
JYKL88
Highly Voted 1 year, 11 months agocwilson91
1 year, 10 months agoDavid983
1 year, 6 months agoSuldan
Most Recent 1 week, 1 day agoljz
1 month, 4 weeks ago462729f
2 months agoKim222
8 months agoKennyMuffins
1 year, 3 months agojosephsafiran
1 year, 3 months agoxcjxcj
1 year, 5 months ago[Removed]
1 year, 5 months agovictory108
1 year, 8 months agoPaulPMP
2 years, 1 month agoPMPStudent
2 years, 4 months agoFranco11
2 years, 6 months ago