Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 57 discussion

Actual exam question from PMI's PMP
Question #: 57
Topic #: 1
[All PMP Questions]

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations.
Which two tools should the project manager use to analyze team performance? (Choose two.)

  • A. Burndown chart
  • B. Product backlog burnup chart
  • C. Cumulative flow diagram of completed features
  • D. Work breakdown structure (WBS)
  • E. Project schedule
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
AbbasTaki
Highly Voted 11 months, 2 weeks ago
Selected Answer: AC
A. Burndown chart: The burndown chart tracks the progress of work completed against the planned work over time. It provides a visual representation of the team's progress and helps identify any deviations from the planned trajectory. By analyzing the burndown chart, the project manager can assess whether the team is falling behind, maintaining a steady pace, or accelerating, allowing them to take corrective actions if necessary. C. Cumulative flow diagram of completed features: The cumulative flow diagram tracks the flow of work items through different stages of the project. It provides a visual representation of the work in progress and can highlight bottlenecks or areas where work is piling up. By analyzing the cumulative flow diagram, the project manager can identify any blockages or inefficiencies that may be hindering the team's momentum and take steps to address them.
upvoted 13 times
...
mrwriting
Most Recent 2 weeks, 1 day ago
Selected Answer: BC
B is better than A: burndown does not correctly if the scope changes
upvoted 1 times
...
58e5964
3 months, 1 week ago
Selected Answer: AB
Fell for the trap myself. The explanation for C is wrong so it would not apply. Cumulative Flow diagram shows the progress of all three metrics (total, in progress and completed). Not just the completed features.
upvoted 1 times
...
BuviD
3 months, 4 weeks ago
Selected Answer: AC
A. Burndown chart and C
upvoted 1 times
...
YUCHAN2022
4 months ago
Chat GPT showed A&C
upvoted 1 times
...
Lhenica
5 months ago
Selected Answer: AC
For me A&C are correct answers
upvoted 1 times
...
GabMonterey
5 months ago
Selected Answer: AB
A & B is correct answer
upvoted 1 times
...
Omar_icon
6 months, 3 weeks ago
Selected Answer: AB
check the trend of what was done (burnup chart) and what is in progress (burndown chart) CFD will show the bottleneck not to track the progress
upvoted 1 times
...
DipeshVora
7 months, 4 weeks ago
Selected Answer: AB
A & B are correct.
upvoted 3 times
...
Goku_PMP
8 months, 3 weeks ago
Selected Answer: B
As team was performing fine in earlier iteration, the best way is to review backlog burn up. There may be chances that team is performing all the user stories, but in recent iteration UserStories might have increased. The best way is to refer backlog burn up chart
upvoted 2 times
...
vivijain
8 months, 4 weeks ago
Selected Answer: AC
A & C are correct.
upvoted 1 times
...
MKWONG
9 months, 2 weeks ago
Selected Answer: AC
agree with A, C
upvoted 1 times
...
smartrammy
10 months ago
Selected Answer: AC
A. Burndown chart C. Cumulative flow diagram of completed features
upvoted 2 times
...
Virtuous
10 months, 1 week ago
Selected Answer: AB
The Answer should focus on Agile performance measurements
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: AC
A. Burndown chart C. Cumulative flow diagram of completed features
upvoted 1 times
...
Digester
12 months ago
Selected Answer: AC
B. Product backlog burndown chart? sounds like a fake term to confuse people.
upvoted 2 times
...
JMCCRAY
1 year ago
Selected Answer: AC
A. Burndown chart: A burndown chart shows the progress of the team in completing the work during each sprint. It helps the project manager to identify if the team is on track to complete the work as planned or if they are falling behind. C. Cumulative flow diagram of completed features: A cumulative flow diagram shows the flow of work through different stages of the development process. It can help the project manager to identify bottlenecks and areas where work is piling up, which may be causing the team to lose momentum.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...