exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 279 discussion

Actual exam question from PMI's PMP
Question #: 279
Topic #: 1
[All PMP Questions]

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a problem in the operations department.
What should the project manager do?

  • A. Escalate the situation to the project sponsor.
  • B. Free the resource to handle the operations priority.
  • C. Ask the manager to submit a change request.
  • D. Design a negotiation strategy for this situation.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
7 months ago
Selected Answer: D
D. Design a negotiation strategy for this situation
upvoted 1 times
...
Only12go
7 months, 1 week ago
Selected Answer: D
D. Designing a negotiation strategy allows the project manager to discuss with the manager the importance of the SME to the project's completion, and perhaps they can reach a compromise. For instance, the SME might split their time or prioritize the most critical tasks first. It's a proactive approach that addresses the immediate need without escalating or introducing potential delays.
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: D
D. Design a negotiation strategy for this situation
upvoted 2 times
...
SteAle
10 months, 4 weeks ago
Selected Answer: D
A PM should always try to fix (in this case by negotiating) prior to escalating to the sponsor
upvoted 2 times
...
AbbasTaki
11 months, 4 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
AP2023S
1 year ago
Selected Answer: C
Why not C?
upvoted 2 times
...
poohwinniewong
1 year, 6 months ago
Why not A?
upvoted 1 times
arnibert
1 year, 5 months ago
Escalation should always come last
upvoted 2 times
JYKL88
1 year ago
but isnt this the last resort already? with schedule behind time, money use up. what else can the PM do? escalate it to resolve this in order to complete the project in time and within budget
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...