exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 166 discussion

Actual exam question from PMI's PMP
Question #: 166
Topic #: 1
[All PMP Questions]

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project time lines have slipped, and the staff is overwhelmed.
What should the project manager do to help the company meet their financial objectives?

  • A. Prioritize the projects, giving higher priority to projects that will increase profit
  • B. Ensure that all of the projects are of high quality and are delivered on time
  • C. Request that upper management hire additional staff to support the projects
  • D. Make sure the project is fast tracked so that slipped time lines are recovered
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Deemmoh
3 months ago
Selected Answer: D
The question says they have innovative projects and the sponsor has responsibility to prioritize. So the only thing the PM can do is to work on time lines to ensure value is achieved for every money spent
upvoted 1 times
...
huynq185
6 months, 2 weeks ago
Selected Answer: A
Answer is A
upvoted 1 times
...
Tuanit
7 months, 1 week ago
Selected Answer: A
I choose A
upvoted 1 times
...
BakM
7 months, 2 weeks ago
Selected Answer: D
the project manager is not supposed to prioritize the projects. and this project manager may not have views on the benefits from other projects.
upvoted 1 times
SerMak
6 months, 3 weeks ago
what project? it doesnt say he is assigned to a specific project. It also doesnt mention that the projects are agile so only the product owner has the authority to prioritize. A is the right one.
upvoted 1 times
...
...
victory108
11 months, 2 weeks ago
Selected Answer: A
A. Prioritize the projects, giving higher priority to projects that will increase profit
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago