Exam CAPM topic 1 question 250 discussion

Actual exam question from PMI's CAPM
Question #: 250
Topic #: 1
[All CAPM Questions]

What process in Project Risk Management prioritizes project risks?

  • A. Perform Qualitative Risk Analysis
  • B. Perform Quantitative Risk Analysis
  • C. Plan Risk Responses
  • D. Implement Risk Responses
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
missyi
Highly Voted 1 year, 11 months ago
PMBOK 6th Ed. 11.3. The answer is A - Perform Qualitative Risk Analysis - the process of prioritizing project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
upvoted 7 times
...
041ba31
Most Recent 11 months ago
A. Perform Qualitative Risk Analysis The process in Project Risk Management that prioritizes project risks is "Perform Qualitative Risk Analysis." In this process, project risks are assessed and prioritized based on their impact and probability. Qualitative risk analysis assigns a risk rating to each identified risk, allowing project managers to focus their attention on the most significant and potentially impactful risks. This prioritization helps in determining which risks require further analysis (quantitative risk analysis) and which risks require the development of risk response plans (plan risk responses).
upvoted 1 times
...
[Removed]
1 year, 4 months ago
Selected Answer: A
Definitely Perform Qualitative Risk Analysis.
upvoted 1 times
...
Daiva
1 year, 4 months ago
Answer A perform qualitative risk analysis. Do not understand why it says Correct answer C when clearly it isn't....
upvoted 1 times
...
PM01950
1 year, 4 months ago
Selected Answer: A
Perform Qualitative Risk Analysis
upvoted 1 times
...
bramirezb593
1 year, 5 months ago
Right answer is A: 11.3 Perform Qualitative Risk Analysis—The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
upvoted 1 times
...
pbbade
1 year, 7 months ago
Selected Answer: A
the right answer
upvoted 2 times
...
AZIZ196
1 year, 12 months ago
actual answer is A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago