PMBOK 6th Ed. 11.3. The answer is A - Perform Qualitative Risk Analysis - the process of prioritizing project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
A. Perform Qualitative Risk Analysis
The process in Project Risk Management that prioritizes project risks is "Perform Qualitative Risk Analysis." In this process, project risks are assessed and prioritized based on their impact and probability. Qualitative risk analysis assigns a risk rating to each identified risk, allowing project managers to focus their attention on the most significant and potentially impactful risks. This prioritization helps in determining which risks require further analysis (quantitative risk analysis) and which risks require the development of risk response plans (plan risk responses).
Right answer is A: 11.3 Perform Qualitative Risk Analysis—The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
missyi
Highly Voted 1 year, 11 months ago041ba31
Most Recent 11 months ago[Removed]
1 year, 4 months agoDaiva
1 year, 4 months agoPM01950
1 year, 4 months agobramirezb593
1 year, 5 months agopbbade
1 year, 7 months agoAZIZ196
1 year, 12 months ago