D. Keeps the focus on the position of the stakeholder or group with respect to the project team
The hierarchical focus of stakeholder communications serves to keep the focus on the position of the stakeholder or group with respect to the project team. In other words, it helps in understanding the level of influence, interest, and importance that various stakeholders or stakeholder groups have in relation to the project. By categorizing stakeholders hierarchically, project managers can tailor their communication strategies and efforts based on the specific needs, expectations, and concerns of different stakeholder levels. This approach helps in managing stakeholder relationships effectively and ensuring that communication efforts are targeted appropriately.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
041ba31
1 year ago[Removed]
1 year, 5 months agoPM01950
1 year, 5 months agosapku
1 year, 7 months agoHungdv
1 year, 9 months agoanfacer
1 year, 12 months agoAZIZ196
2 years ago