A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

  • A. Add a subject matter expert (SME) to the project team.
  • B. Fill the skill gap personally to execute the project.
  • C. Allow the team to proceed as they attempt to meet the timeline.
  • D. Invite stakeholders to discuss a mitigation plan to finish on time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
teslamaster
Highly Voted 2 years, 2 months ago
Selected Answer: A
A should be the correct one..
upvoted 9 times
EA1234
2 years, 2 months ago
Why not D?
upvoted 1 times
...
Bobbie30
2 years, 2 months ago
I agree. A should be the correct answer
upvoted 5 times
...
...
8a6d137
Most Recent 3 weeks, 3 days ago
Selected Answer: A
Key word to pay attention to is "HARD TIMELINE" They know that dont have skill right from first iteration. if timeline was not hard they could have sent developers on training and built skill gradually but they dont have time so best course of action is A.
upvoted 1 times
...
LNX_RM_Admin
8 months, 3 weeks ago
Selected Answer: D
First meeting with stakeholder.
upvoted 1 times
...
9RedFox_JB
10 months, 1 week ago
Just had a discussion about familiar situation with a project member. Team member indicates that SME is needed but Project ignores. and the answer C would lead to a work that has to be redone several times in this case, increased risks of future issues. answer A would be most efficient one if looking from quality and time perspective(having in mind that everyone would be sharing their knowledge) off course if team takes full responsibility maybe answer C is correct, but....
upvoted 1 times
...
NadirJT
10 months, 2 weeks ago
Selected Answer: D
Add a subject matter expert (SME) to the project team. is a result of Stakeholders Consensus. So stakeholder first, cost/risk consideration, then adding a SME. Not just cause Project Manager "Decided"
upvoted 4 times
...
urso2703
10 months, 2 weeks ago
Selected Answer: C
Initially went with A, but after reading back, I understand why its C. It's still the first Iteration. Let the team get adjusted and gather more understanding and data.
upvoted 3 times
...
Abdelmonm
1 year ago
Selected Answer: A
When a project team lacks the necessary skills to execute a project, adding a subject matter expert (SME) to the team is a proactive step to address the skill gap. The SME can contribute specialized knowledge and expertise, helping the team overcome challenges and ensuring the project progresses successfully. This is a practical approach to enhance the team's capabilities and increase the likelihood of meeting the project timeline.
upvoted 2 times
...
odylec
1 year, 1 month ago
Selected Answer: D
D is the answer
upvoted 1 times
...
6thEditionAndy
1 year, 2 months ago
Selected Answer: D
D is the right answer. A is wrong because you cant expand or reduce the project team without the required formal approvals. The outcome of D will however likely end up with A.
upvoted 3 times
...
Aymen1989
1 year, 3 months ago
Answer D before B
upvoted 1 times
Aymen1989
1 year, 3 months ago
I mean before A
upvoted 1 times
...
...
Only12go
1 year, 3 months ago
Selected Answer: A
When a project team lacks the necessary skills to execute a project with a hard timeline, the project manager should take action to address this skill gap effectively. Option A is the most appropriate response: A. Add a subject matter expert (SME) to the project team.
upvoted 2 times
iuedeme
10 months, 4 weeks ago
A- Expert judgement
upvoted 1 times
...
...
adingmaki
1 year, 3 months ago
PMBOK 7th page 40. A To those who answered D? What exactly will be your risk mitigation? Bring in an SME?
upvoted 2 times
...
David983
1 year, 3 months ago
Selected Answer: D
Does the Agile Methogology based on PM take the decisions by himself or Agile is based in team collaboration and team decision? According team decition on Agile Methods I will go with D, PM is a facilitator and stakeholders must decide based on discussion
upvoted 2 times
...
ChezQW
1 year, 4 months ago
Selected Answer: A
Adding a SME would bridge the gap and help the team to hit the hard timeline in my opinion.
upvoted 2 times
...
victory108
1 year, 4 months ago
Selected Answer: A
A. Add a subject matter expert (SME) to the project team
upvoted 2 times
...
kayyaly
1 year, 5 months ago
Selected Answer: D
D. Invite stakeholders to discuss a mitigation plan to finish on time. Must discuss first the best solution with the stakeholders, training, SME or any other solution
upvoted 3 times
...
SynikalDemon
1 year, 5 months ago
Selected Answer: A
It's A
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...