exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 691 discussion

Actual exam question from PMI's PMP
Question #: 691
Topic #: 1
[All PMP Questions]

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

  • A. Probabilistic analysis was used to develop the budget to address future uncertainties.
  • B. The budget was developed by using the lessons learned from previous project data.
  • C. Recurrent team meetings are planned to control the budget against future uncertainties.
  • D. Feedback from stakeholders will be addressed at each board meeting to adapt the budget.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
noppy
Highly Voted 1 year, 4 months ago
Selected Answer: A
The correct answer is A. Refer to PMBOK 7 "2.4.2.2 Estimating" p. 57 "Deterministic and probabilistic estimating. Deterministic estimates, also known as point estimates, present a single number or amount, such as 36 months. Probabilistic estimates include a range of estimates along with the associated probabilities within the range. They can be developed manually by (a) developing a weighted average based on multiple likely outcomes, or (b) running a simulation to develop a probability analysis of a particular outcome, usually in terms of cost or schedule"
upvoted 6 times
...
Abdelmonm
Most Recent 9 months ago
Selected Answer: A
This indicates that the project manager employed a method that accounts for uncertainties and risks in the budgeting process. Probabilistic analysis involves considering a range of possible outcomes with associated probabilities, providing a more comprehensive and realistic approach to budgeting, particularly in the face of uncertainties.
upvoted 1 times
...
Nassim_Paco
10 months, 2 weeks ago
C. Recurrent team meetings are planned to control the budget against future uncertainties. Is the correct answer.
upvoted 2 times
...
Only12go
1 year ago
Selected Answer: A
A. Probabilistic analysis involves considering various possible scenarios and their associated probabilities to develop a budget that accounts for future uncertainties. It is a common technique in project management to address the inherent risks and uncertainties in project budgets.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Probabilistic analysis was used to develop the budget to address future uncertainties
upvoted 1 times
...
Aesam
1 year, 2 months ago
Selected Answer: A
PMBOK 7 2.4.2.2
upvoted 2 times
...
Aish_
1 year, 2 months ago
Selected Answer: A
Voting for A. As the question is, how the budget was developed for future uncertainties. C is only a way to track in future.
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: B
I am really confused. The budget normally gets determined and approved at the end of the planning phase, not the initiation phase. If this is what they meant in the question, then the answer should be A. Otherwise, the only sensible answer is B. Probabilistic analysis is used in the Performed Quantitative Risk analysis process (PMBOK "Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.". while are "at the end of a project's initiation phase".
upvoted 1 times
...
Dawn6699
1 year, 4 months ago
Selected Answer: A
It should be A
upvoted 1 times
...
Faozi
1 year, 5 months ago
Selected Answer: A
A directly addresses the stakeholder's concern by explaining that probabilistic analysis was employed during budget development to account for future uncertainties. This response demonstrates that the project manager considered potential uncertainties and used a systematic approach to develop a budget that can adapt to those uncertainties. C, which states that recurrent team meetings are planned to control the budget against future uncertainties, is not the best choice because it primarily addresses the ongoing control and monitoring of the budget, rather than how the budget was developed to address future uncertainties. While recurrent team meetings can be an effective method for monitoring and controlling the budget throughout the project, they do not directly address how the budget was developed to account for uncertainties during the initiation phase. The stakeholder's question is specifically about the process used for budget development and not about ongoing budget control measures.
upvoted 4 times
...
Hung3102
1 year, 6 months ago
A. Probabilistic analysis was used to develop the budget to address future uncertainties. Probabilistic analysis is a technique used to account for uncertainties and risks in project budgeting. The project manager should reply that probabilistic analysis was used to develop the budget to address future uncertainties. This technique involves estimating the probability of different outcomes and assigning values to those outcomes, which are then used to develop a budget that accounts for those uncertainties. By using probabilistic analysis, the project manager can account for potential risks and uncertainties in the project budget, ensuring that the project is adequately funded to deal with any unforeseen events that may arise
upvoted 4 times
...
RevZig67
1 year, 6 months ago
Selected Answer: A
By using probabilistic analysis, the project manager can identify the likelihood of different scenarios and outcomes, and incorporate them into the budget. This approach can help address future uncertainties and ensure that the project budget is realistic and flexible.
upvoted 2 times
...
mrbottomwood
1 year, 7 months ago
I'd go with option A. The keyword here to me is "future uncertainties" -- meaning some outcomes that will associated with cost may occur. Probabilistic analysis is a technique used to assess the likelihood of different scenarios and their potential impact on the project budget. By using probabilistic analysis, the project team can develop a budget that takes into account future uncertainties and their potential impact on the project.
upvoted 2 times
...
Ragaa
1 year, 9 months ago
C makes sense to me. Lesson learnt should not drive the budget.
upvoted 2 times
...
poohwinniewong
1 year, 10 months ago
Should be b
upvoted 2 times
...
poohwinniewong
1 year, 11 months ago
Is the ans correct?
upvoted 1 times
...
KA90
1 year, 11 months ago
Selected Answer: B
Stakeholder is not asking about controlling the budget, he is asking how it was developed for future uncertainties, B makes more sense.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago