A project for Company A was successfully delivered within scope, schedule, and budget by the end of the last iteration. However, during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?
Adeshola1960
Highly Voted 2 years, 3 months agoprokat_mashin_na_vicecity
1 year, 6 months agomjs
Highly Voted 2 years, 5 months agoSuldan
Most Recent 1 week, 3 days agoAnne99
3 weeks, 1 day ago462729f
2 months, 1 week agoNgho
6 months, 3 weeks agoea4e1f8
8 months agotonybuivannghia
9 months, 1 week agoUppersquareCapital
1 year, 1 month agoBruce_Liu
1 year, 3 months agopsvexam
1 year, 3 months agojosephsafiran
1 year, 3 months agoOnly12go
1 year, 6 months agovictory108
1 year, 8 months agoAish_
1 year, 8 months agokevzzz
1 year, 8 months agoprokat_mashin_na_vicecity
1 year, 6 months agoAstridN
1 year, 9 months ago