Exam PMP topic 1 question 758 discussion

Actual exam question from PMI's PMP
Question #: 758
Topic #: 1
[All PMP Questions]

A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?

  • A. Release the team and help them achieve their potential on a new project.
  • B. Pause the project if business value cannot be reached and collect lessons learned.
  • C. Assess the environmental changes and recommend a pivot for the project.
  • D. Ask the organization's management for advice regarding the project's direction.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KA90
Highly Voted 1 year, 11 months ago
Selected Answer: C
Correct answer is C
upvoted 10 times
...
15rajanikanthhotie
Highly Voted 1 year, 10 months ago
Selected Answer: C
Assess the environmental changes and recommend a pivot for the project
upvoted 5 times
...
Abdelmonm
Most Recent 9 months ago
Selected Answer: C
In the face of unforeseen events that render the current features and solution less usable due to new travel restrictions, assessing the environmental changes and recommending a pivot for the project is a proactive and strategic approach. This involves evaluating the project's alignment with the current business environment and proposing necessary adjustments or changes to maximize business value. It allows the project manager to adapt to the new circumstances and consider alternative directions that can still provide value to the organization.
upvoted 1 times
...
chlaithem
9 months, 3 weeks ago
Selected Answer: C
Proactive response: Analyzing the impact of new travel restrictions and actively seeking alternative directions demonstrates initiative and problem-solving skills. Consideration of value: Pivoting aims to adapt the project to the changed context and potentially deliver value even with adjustments. This prioritizes efficient resource utilization and minimizing sunk costs. Informed decision-making: Thorough assessment provides a basis for proposing well-grounded recommendations on how to adapt the project to the new environment.
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: C
C. Assessing the environmental changes and recommending a pivot for the project is a proactive step that focuses on understanding the situation and exploring potential solutions. This step addresses the immediate need to reassess the situation given the new travel restrictions and aligns with agile and adaptive project management practices.
upvoted 1 times
...
Sumbo
1 year ago
Selected Answer: C
definitely C
upvoted 1 times
...
victory108
1 year ago
Selected Answer: C
C. Assess the environmental changes and recommend a pivot for the project
upvoted 1 times
...
Cocs
1 year, 1 month ago
C is the correct answer, refer to PMBOK 7 page 209. ... If the market changes or the organization’s goals shift, work with the project team to pivot the direction of the project to meet the current needs.
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: C
By performing a thorough assessment and considering a pivot, the project manager can make informed decisions about the project's future, ensuring that it remains aligned with the startup's goals and can deliver value despite the challenges posed by the travel restrictions. It also demonstrates proactive and adaptive project management, which is crucial in dynamic and uncertain environments.
upvoted 1 times
...
fulcrum501
1 year, 5 months ago
Selected Answer: C
C should be correct
upvoted 1 times
...
emelba
1 year, 6 months ago
Selected Answer: C
Assess the environmental changes and recommend a pilot for the project
upvoted 1 times
...
Mahdi2022
1 year, 8 months ago
Go with C!
upvoted 1 times
...
Jonathans_artisan_pizza
1 year, 9 months ago
Selected Answer: C
I vote C.
upvoted 1 times
...
James10
1 year, 9 months ago
C Never ask for advice
upvoted 1 times
...
hihi2022
1 year, 9 months ago
Selected Answer: C
Correct answer is C
upvoted 2 times
...
Cert_IT
1 year, 10 months ago
Selected Answer: C
it should be C
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago