Actual exam question from PMI's PMP
Question #: 365
Topic #: 1
[All PMP Questions]

During an ongoing project, a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy.
What should the project manager share with the key resource?

  • A. The updated project management plan
  • B. The updated benefits management plan
  • C. The updated communications management plan
  • D. The updated scope management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
akaki
Highly Voted 1 year, 11 months ago
Selected Answer: B
Project objectives and the organization's strategy should be described in the Benefit Management Plan.
upvoted 9 times
...
SAJSAJ
Most Recent 7 months ago
Should be option A.
upvoted 1 times
...
josephsafiran
9 months, 3 weeks ago
Selected Answer: B
The project manager should choose option B. The updated benefits management plan. This plan outlines the benefits of the project and how it aligns with the organization’s strategy. It provides a clear understanding of the project’s purpose and its strategic alignment. Sharing this with the key resource can help them understand the value of their work in the context of the organization’s goals
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: B
B. The updated benefits management plan
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: B
B. The updated benefits management plan
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: B
PMBOK 6: BMP contains "Strategic alignment (e.g., how well the project benefits align to the business strategies of the organization);"
upvoted 1 times
...
aqz_111
1 year, 4 months ago
Selected Answer: A
One of project management plan is scope base line which has WBS + Scope statement. The scope statement has project objective which can tell you whether the project is aligned with organisation's objective.
upvoted 1 times
...
AP2023S
1 year, 5 months ago
Selected Answer: A
Why not A? Tthe PMP contains all the other plans within itself and therefore has all the required information
upvoted 3 times
...
Bolumighty
1 year, 11 months ago
Selected Answer: D
Benefit Management Plan does not seem right. D is more appropriate
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago