During an ongoing project, a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy. What should the project manager share with the key resource?
The project manager should choose option B. The updated benefits management plan. This plan outlines the benefits of the project and how it aligns with the organization’s strategy. It provides a clear understanding of the project’s purpose and its strategic alignment. Sharing this with the key resource can help them understand the value of their work in the context of the organization’s goals
One of project management plan is scope base line which has WBS + Scope statement. The scope statement has project objective which can tell you whether the project is aligned with organisation's objective.
Benefit Management Plan does not seem right. D is more appropriate
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
akaki
Highly Voted 1Â year, 11Â months agoSAJSAJ
Most Recent 7Â months agojosephsafiran
9Â months, 3Â weeks agoLucky_Cindy
1Â year agovictory108
1Â year, 2Â months agoSteAle
1Â year, 3Â months agoaqz_111
1Â year, 4Â months agoAP2023S
1Â year, 5Â months agoBolumighty
1Â year, 11Â months ago