exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 678 discussion

Actual exam question from PMI's PMP
Question #: 678
Topic #: 1
[All PMP Questions]

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

  • A. Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.
  • B. Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.
  • C. Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.
  • D. Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PMPStudent
Highly Voted 1 year, 10 months ago
Selected Answer: C
I would go with C.
upvoted 6 times
...
Abdelmonm
Most Recent 9 months ago
Selected Answer: C
Identifying the critical path and understanding the reasons for the potential schedule delay are crucial steps in addressing and managing the situation. By focusing on the critical path and investigating the root causes of the delay, the project manager can develop a more targeted and effective plan for schedule recovery. This proactive approach allows the project manager to address the specific issues causing the delay and take corrective actions to bring the project back on track.
upvoted 3 times
...
chlaithem
9 months, 3 weeks ago
Selected Answer: C
Immediate investigation is crucial: Early intervention: Identifying the cause of the delay early allows for swift corrective action to minimize its impact on the overall project timeline. Accurate assessment: Without understanding the specific activities causing the delay, it's difficult to accurately predict the extent of the delay and effectively propose solutions. Targeted solutions: By pinpointing the cause, the project manager can develop targeted solutions, potentially avoiding unnecessary resource requests or communication causing undue worry.
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: C
In a situation where there might be a schedule delay in a multiyear resource-constrained project that is midway through the execution phase, and the team is working hard with many deliverables completed, the project manager should take immediate action to assess the situation and identify the causes of the potential delay. The most appropriate action is: C. Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay
upvoted 1 times
...
error_909
1 year, 2 months ago
find the reason, add risk, change request, then updating schedule
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: C
Option D suggests asking the scheduler to update the schedule with the percent of work in progress (WIP) and communicating the results to the team. While this step may provide information about the current progress of the project, it does not directly address the issue of schedule delay that has been identified during the progress update meeting. In contrast, option C is more appropriate because it focuses on understanding the specific reasons for the schedule delay by identifying the critical path and delayed activities. This investigation will provide valuable insights into the root causes of the delay, enabling the project manager to take targeted actions to address the issues and minimize the impact on the project timeline.
upvoted 2 times
...
Hung1
1 year, 6 months ago
You need to know the root cause of delayed first, then action. C should be answer.
upvoted 1 times
...
mangostiffy
1 year, 6 months ago
I'll go with A
upvoted 1 times
...
emelba
1 year, 6 months ago
Selected Answer: C
I would go with C, it seems there are too many bugs in this dump
upvoted 2 times
...
Alizade
1 year, 7 months ago
Selected Answer: C
C. Ask the project planner to identify the critical path and respective delayed activities and then investigate the reasons for the delay. The project manager should first identify the specific causes of the potential schedule delay by analyzing the critical path and determining which activities are delayed. This will help to pinpoint the problem areas and identify potential solutions to address the issue. Once the reasons for the delay are understood, the project manager can develop an appropriate plan to mitigate the risks and get the project back on track.
upvoted 1 times
...
sanjiiv
1 year, 7 months ago
Selected Answer: C
C is best among all
upvoted 1 times
...
spamgayy
1 year, 7 months ago
Definitely C... the deliverables on the critical path are the ones that matter
upvoted 1 times
...
rajeshtk
1 year, 7 months ago
It should be C.
upvoted 1 times
...
modsjunk
1 year, 10 months ago
Selected Answer: A
there might be a schedule delay to deliver the project <- Risk C says respective delayed activities, there is no real delay yet Answer is A
upvoted 2 times
PMPStudent
1 year, 10 months ago
It is definitely not A.
upvoted 1 times
...
...
poohwinniewong
1 year, 10 months ago
Should it be C?
upvoted 1 times
...
YYemi
1 year, 11 months ago
not A, apparently
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago