You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
A.
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
The Program Management Standard clearly states that projects are initiated in the Delivery Phase. Here that is consistent with "execution" but this question is not updated with the latest information from the standard.
All components initiation happens in the Program execution phase.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PgMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
f07e1dd
1 month agoCindyl
2 years, 2 months ago