exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 431 discussion

Actual exam question from PMI's PgMP
Question #: 431
Topic #: 1
[All PgMP Questions]

When should a program manager approve the closure of a component project?

  • A. When acceptance criteria of the project are met
  • B. When the project has delivered the project benefits
  • C. When program deliverables are complete
  • D. When project deliverables are complete
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
10 months, 1 week ago
Selected Answer: A
A. When acceptance criteria of the project are met. Approval of project closure should be based on whether the project has met its predefined acceptance criteria. These criteria are usually established at the beginning of the project and are designed to define what constitutes successful completion of the project. Meeting the acceptance criteria ensures that the project has achieved its objectives, even if the full benefits of the project might only be realized later in the context of the overall program. This focus on acceptance criteria allows for a clear and objective measure to decide on project closure.
upvoted 1 times
...
hanyulin
11 months ago
Selected Answer: D
Sorry, D is the right answer. Projects must deliver results before close.
upvoted 1 times
...
[Removed]
11 months ago
Selected Answer: A
A. When acceptance criteria of the project are met. The closure of a component project should be approved by the program manager when the project's acceptance criteria are met. These criteria are predefined measures or conditions that determine when the project's outputs are completed to a satisfactory level. It's important to note that project deliverables can be completed, but they still need to meet the agreed-upon acceptance criteria to ensure they align with the required standards and specifications. Approval upon meeting these criteria ensures that the project has fulfilled its objectives and its outcomes are of the expected quality.
upvoted 1 times
...
hanyulin
11 months, 2 weeks ago
Selected Answer: A
A is the right answer.
upvoted 1 times
...
ekk1983
1 year ago
I think A is the Answer
upvoted 1 times
...
NawrasHamwi
1 year, 10 months ago
No need to wait until Program deliverables are complete to close a component project, probably A
upvoted 1 times
...
Salim_7
1 year, 12 months ago
I picked A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...