A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion.
What are two issues that these actions by the project manager could cause? (Choose two.)
Anssoo
3 months, 1 week agoKim222
11 months, 2 weeks agoOnly12go
1 year, 9 months agovictory108
1 year, 11 months agoAish_
2 years agoAkhundzada
2 years agosmartrammy
2 years, 1 month agoJamrock
2 years agocwilson91
2 years, 2 months agonoppy
2 years, 2 months agoJamrock
2 years agoduyun
2 years, 2 months agoclarksu
2 years, 3 months agoJamrock
2 years agoadviselee
2 years, 3 months agosnagile
2 years, 3 months agoJamrock
2 years agoVPNalumni
2 years, 3 months agoJamrock
2 years agoJamrock
2 years agoHung3102
2 years, 4 months agoJamrock
2 years agoHung1
2 years, 3 months agoAdeshola1960
2 years, 5 months agoJamrock
2 years agoMBoo93
2 years, 6 months agoDoughSu
2 years, 7 months agoJamrock
2 years agoakcisa_79
2 years, 3 months agoJamrock
2 years ago