A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 1 year, 11 months agosegatarasov
1 year, 2 months agoadingmaki
Highly Voted 1 year, 6 months agoApaMokus
Most Recent 5 days, 14 hours agoSuldan
1 week, 4 days agoAgratsant
1 month, 4 weeks agoWWu
2 months, 3 weeks agokrispara
4 months agovlxx
5 months, 1 week agoAmirov
6 months agoKim222
8 months, 3 weeks agoLNX_RM_Admin
11 months agoMartinussantika
11 months, 1 week agoShittu1
1 year, 2 months agojosephsafiran
1 year, 2 months agoshawndude
1 year, 3 months agojosephsafiran
1 year, 3 months agoBruce_Liu
1 year, 3 months ago