A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 2 years, 1 month agosegatarasov
1 year, 4 months agoadingmaki
Highly Voted 1 year, 8 months agokoffeebrown
Most Recent 1 month, 3 weeks agoApaMokus
2 months agoSuldan
2 months, 1 week agoAgratsant
3 months, 4 weeks agoWWu
4 months, 3 weeks agokrispara
6 months agovlxx
7 months, 1 week agoAmirov
8 months agoKim222
10 months, 3 weeks agoLNX_RM_Admin
1 year, 1 month agoMartinussantika
1 year, 1 month agoShittu1
1 year, 4 months agojosephsafiran
1 year, 4 months agoshawndude
1 year, 5 months agojosephsafiran
1 year, 5 months ago