A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 2 years, 2 months agosegatarasov
1 year, 5 months agoadingmaki
Highly Voted 1 year, 10 months agocococua
Most Recent 3 weeks, 3 days agoDanny_120704
1 month, 2 weeks agokoffeebrown
3 months, 1 week agoApaMokus
3 months, 3 weeks agoSuldan
3 months, 4 weeks agoAgratsant
5 months, 2 weeks agoWWu
6 months, 1 week agokrispara
7 months, 2 weeks agovlxx
8 months, 3 weeks agoAmirov
9 months, 3 weeks agoKim222
1 year agoLNX_RM_Admin
1 year, 2 months agoMartinussantika
1 year, 2 months agoShittu1
1 year, 5 months agojosephsafiran
1 year, 6 months ago