A team is holding the first demonstration of the software built to date on a medium-sized project. The product owner has uncovered a number of issues they would like to be addressed before providing approval.
How should the project manager approach this problem?

  • A. Plan to address the issues through backlog grooming and incorporate them into the next sprint
  • B. Refer the product owner to the change management plan, then escalate to the steering committee
  • C. Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes
  • D. Tell the product owner the issues will be addressed in the second version of the software
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: A
This is just first demo and PO has a lot of feedback so PM & team just need to address the comment and add its to backlog for the next iteration
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: A
A. Plan to address the issues through backlog grooming and incorporate them into the next sprint
upvoted 1 times
...
noppy
1 year, 11 months ago
I'm not sure A is correct because project manager is allowed to do backlog grooming. As I checked, backlog is managed by product owner or manager. Then.. what would be the answer?
upvoted 2 times
...
Thirukj
1 year, 11 months ago
Selected Answer: A
A is right
upvoted 1 times
...
Alizade
2 years, 1 month ago
Selected Answer: A
A. Plan to address the issues through backlog grooming and incorporate them into the next sprint. The product owner's feedback is valuable, and it is crucial to address the issues they have raised in a timely and effective manner. Incorporating these issues into the backlog and addressing them in the next sprint will help ensure that the software meets the product owner's needs and expectations.
upvoted 2 times
...
Bobbie30
2 years, 5 months ago
Can someone please help with this? I'm totally lost
upvoted 1 times
15rajanikanthhotie
2 years, 5 months ago
Demo means sprint review, in completed items will be added to backlog and then to to next sprint
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...