Question #: 639
Topic #: 1
[All PMP Questions]

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

  • A. Escalate to management for approval since the change was not included in the original requirements.
  • B. Tell the customer that the requirement change will be put into the next project phase if management approves.
  • C. Give the change to the scrum master to investigate how much additional effort the change will require.
  • D. Validate the requirement change with the product owner and development team before redefining the scope.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months, 1 week ago
Selected Answer: D
D. Validate the requirement change with the product owner and development team before redefining the scope
upvoted 1 times
...
AbbasTaki
10 months, 2 weeks ago
Selected Answer: C
In an agile environment, the scrum master is responsible for helping the team to deliver the product according to the sprint goal. This includes helping the team to manage changes to the product backlog, which is the list of features and functionality that the team will deliver in the next sprint. If a customer requirement change is discovered during a daily meeting, the scrum master can help the team to assess the impact of the change on the sprint backlog. This includes estimating how much additional effort the change will require and whether or not the change can be accommodated in the current sprint. The scrum master can also help the team to communicate the change to the product owner and to get the product owner's approval for the change. If the product owner approves the change, the scrum master can then help the team to incorporate the change into the sprint backlog. Therefore, option C is the most appropriate answer to the question. By giving the change to the scrum master, the project manager can ensure that the change is carefully considered and that the team has the support they need to implement the change smoothly and effectively.
upvoted 1 times
Jamrock
8 months, 1 week ago
I think your answer said the right thing but came to the wrong conclusion. C. never mentions anyone else so it was wrong: The scrum master's role is to facilitate the Agile process, but the decision-making should involve the entire team and align with Agile principles.
upvoted 1 times
...
...
[Removed]
1 year ago
Selected Answer: D
Validate the requirement change with the product owner and development team before redefining the scope.
upvoted 3 times
...
[Removed]
1 year ago
Validate the requirement change with the product owner and development team before redefining the scope.
upvoted 1 times
...
Alizadeh
1 year, 3 months ago
Selected Answer: D
The correct answer is B. Validate the requirement change with the product owner and development team before redefining the scope. If a project manager discovers a customer requirement change during a daily meeting in a frequently changing project, it is important to carefully assess the impact of the change before proceeding. The project manager should validate the requirement change with the product owner and development team to ensure that it is feasible and aligns with the project goals. Based on this assessment, the project manager can then work with the team to redefine the scope as needed and determine any additional effort that may be required. It may also be necessary to escalate the change to management for approval, but this should not be the first step taken. Telling the customer that the requirement change will be put into the next project phase or giving the change to the scrum master to investigate are not appropriate actions, as they do not address the need to validate the change and assess its impact on the project.
upvoted 3 times
...
Bobbie30
1 year, 5 months ago
Please can someone explain why the selected answer is right
upvoted 1 times
Ab5434
1 year, 5 months ago
Basically, in agile projects, it is better to always make changes with the product manager and the development team. Scrum master should also have the role of facilitator.
upvoted 1 times
...
poohwinniewong
1 year, 5 months ago
This seems to be an agile project as it is frequently changing and have daily meeting. For changes, you need to talk with Product Owner.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago