A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.
What should the project manager do first?
Jordarlu
2 months, 3 weeks agoea4e1f8
8 months, 2 weeks agoAbdelmonm
1 year, 3 months agoAntoFE
1 year, 4 months agoodylec
1 year, 4 months ago[Removed]
1 year, 5 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agovictory108
1 year, 7 months agoAish_
1 year, 9 months agocwilson91
1 year, 10 months agoNeil20
1 year, 10 months agonoppy
1 year, 10 months agoVPNalumni
2 years agolongge
2 years, 2 months agoFanboy
2 years, 1 month ago15rajanikanthhotie
2 years, 4 months agomjs
2 years, 5 months agoPMPStudent
2 years, 4 months agoJames10
2 years, 3 months ago