exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 240 discussion

Actual exam question from PMI's PMP
Question #: 240
Topic #: 1
[All PMP Questions]

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?

  • A. Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.
  • B. Instruct the team to make only a graphical representation of all the data for the report.
  • C. Instruct the team to conduct a meeting with the stakeholders before finalizing the report.
  • D. Instruct the team to analyze and interpret the data before including it in the report.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
madusankagd
Highly Voted 8 months, 4 weeks ago
Selected Answer: D
in this scenario, while SOPs may provide a framework for report creation, the immediate focus should be on analyzing and interpreting the gathered data to ensure that the report effectively communicates the project's status and progress to stakeholders. Once the data has been analyzed and interpreted, the team can then follow SOPs to structure and format the report according to established guidelines.
upvoted 5 times
...
ompk
Most Recent 6 months, 3 weeks ago
How come a Project manager instructs to his/her team to make a report. Suppose if a PM has team of engineers who have worked on technical aspects of the on-going project and wanted to make a report on it with technical data. Now, even the data or technical aspects are large how can a project manager instruct them to make a report? SOP are important to follow becuase what if the initial report consist of 5 pages with different specification etc and then the next project report is 10 pages with different topics or instructions. An SOP should be followed while writing a report which may include Summary, Progress, risks, timeline, stages, next steps etc and also in one format. What you guys think?
upvoted 2 times
...
4f6ae44
7 months, 3 weeks ago
Its going back to the the PM Mindset of stick to the plan - so correct answer is "A"
upvoted 3 times
...
josephsafiran
11 months ago
Selected Answer: D
The project manager should **D. Instruct the team to analyze and interpret the data before including it in the report**. This approach ensures that the data is relevant, meaningful, and easily understood by the stakeholders. It also helps to highlight key insights and findings, making the report more valuable and effective. This approach aligns with best practices for data reporting and communication.
upvoted 2 times
...
Bruce_Liu
11 months, 2 weeks ago
Selected Answer: D
Relevance is more important than just follow procedures. ChatGPT also chooses D.
upvoted 1 times
...
Hashi1_snr
1 year ago
Selected Answer: D
Option D is the best choice. Be reminded of agile principle 4 which state thus " Responding to change over following a plan." So by using the SOP, we kill the agile requirement of responding to change. There should be a need for flexibility to take advantage of unplanned emergencies which can only be achieved when the team perform option D to identify any changing conditions that will require attention. SOP keeps the team stereotypical and void of agile mindset. I will die with option D on this scenario.
upvoted 2 times
...
estimater
1 year, 1 month ago
Selected Answer: A
Option A has large identification than D so i am with A
upvoted 3 times
...
Only12go
1 year, 1 month ago
Selected Answer: D
D. Instruct the team to analyze and interpret the data before including it in the report. Explanation: Simply providing a large amount of raw data in a report can be overwhelming and not particularly helpful to stakeholders. The primary purpose of a report is to convey meaningful information that can guide decision-making. To achieve this, data should be analyzed and interpreted to extract key insights and provide a clear picture of the current status, progress, risks, or any other relevant aspects of the project.
upvoted 1 times
...
Tuanit
1 year, 1 month ago
Selected Answer: A
Follow the standard
upvoted 2 times
...
Fyrus
1 year, 2 months ago
Selected Answer: D
I first voted for D and then asked ChatGPT While ensuring the team follows standard operating procedures (SOP) for creating a stakeholder report (option A) is important, it should be complemented by data analysis to enhance the report's value
upvoted 3 times
...
sam1721
1 year, 2 months ago
A- following SOP makes most sense.
upvoted 2 times
...
GinniSingh
1 year, 4 months ago
Selected Answer: A
First team need to know the SOP of stakeholder report.. what to present.. then only PM will ask team to collect, analyze and interpret the relevant data in accordance with the reporting format
upvoted 3 times
...
victory108
1 year, 4 months ago
Selected Answer: D
D. Instruct the team to analyze and interpret the data before including it in the report
upvoted 1 times
...
TomGrey
1 year, 5 months ago
Selected Answer: A
A includes D, and D doesn't include other parameters of A. So A is the best answer.
upvoted 3 times
...
AbbasTaki
1 year, 6 months ago
Selected Answer: D
D is the answer
upvoted 1 times
...
aqz_111
1 year, 7 months ago
I selected D, report for management should be useful for decision making. It should comply the WPI. SOP are templates, report format which are not useful for decision making. I don't think A is correct
upvoted 1 times
...
JMCCRAY
1 year, 7 months ago
Selected Answer: D
D. Instruct the team to analyze and interpret the data before including it in the report. While it is important for the team to follow standard operating procedures (SOP) for creating a stakeholder report, this alone may not ensure the report contains accurate and relevant information. Similarly, presenting only graphical representation of data may not provide sufficient information to stakeholders who may need a more detailed analysis of the project status.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...