Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.
A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report. What should the project manager do next?
A.
Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.
B.
Instruct the team to make only a graphical representation of all the data for the report.
C.
Instruct the team to conduct a meeting with the stakeholders before finalizing the report.
D.
Instruct the team to analyze and interpret the data before including it in the report.
in this scenario, while SOPs may provide a framework for report creation, the immediate focus should be on analyzing and interpreting the gathered data to ensure that the report effectively communicates the project's status and progress to stakeholders. Once the data has been analyzed and interpreted, the team can then follow SOPs to structure and format the report according to established guidelines.
The project manager should **D. Instruct the team to analyze and interpret the data before including it in the report**. This approach ensures that the data is relevant, meaningful, and easily understood by the stakeholders. It also helps to highlight key insights and findings, making the report more valuable and effective. This approach aligns with best practices for data reporting and communication.
Option D is the best choice. Be reminded of agile principle 4 which state thus " Responding to change over following a plan." So by using the SOP, we kill the agile requirement of responding to change. There should be a need for flexibility to take advantage of unplanned emergencies which can only be achieved when the team perform option D to identify any changing conditions that will require attention. SOP keeps the team stereotypical and void of agile mindset. I will die with option D on this scenario.
D. Instruct the team to analyze and interpret the data before including it in the report.
Explanation:
Simply providing a large amount of raw data in a report can be overwhelming and not particularly helpful to stakeholders. The primary purpose of a report is to convey meaningful information that can guide decision-making. To achieve this, data should be analyzed and interpreted to extract key insights and provide a clear picture of the current status, progress, risks, or any other relevant aspects of the project.
I first voted for D and then asked ChatGPT
While ensuring the team follows standard operating procedures (SOP) for creating a stakeholder report (option A) is important, it should be complemented by data analysis to enhance the report's value
First team need to know the SOP of stakeholder report.. what to present.. then only PM will ask team to collect, analyze and interpret the relevant data in accordance with the reporting format
I selected D, report for management should be useful for decision making. It should comply the WPI. SOP are templates, report format which are not useful for decision making. I don't think A is correct
D. Instruct the team to analyze and interpret the data before including it in the report.
While it is important for the team to follow standard operating procedures (SOP) for creating a stakeholder report, this alone may not ensure the report contains accurate and relevant information. Similarly, presenting only graphical representation of data may not provide sufficient information to stakeholders who may need a more detailed analysis of the project status.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
4f6ae44
2 weeks, 1 day agomadusankagd
1 month, 3 weeks agojosephsafiran
3 months, 3 weeks agoBruce_Liu
4 months agoHashi1_snr
5 months, 2 weeks agoestimater
6 months agoOnly12go
6 months, 2 weeks agoTuanit
6 months, 3 weeks agoFyrus
7 months, 1 week agosam1721
7 months, 3 weeks agoGinniSingh
9 months, 2 weeks agovictory108
9 months, 3 weeks agoTomGrey
10 months, 1 week agoAbbasTaki
11 months, 1 week agoaqz_111
12 months agoJMCCRAY
1 year agoHung3102
1 year, 1 month ago