A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
Hung3102
Highly Voted 2 years, 2 months agoHung3102
2 years, 2 months agohayalou
Most Recent 3 days agoSuldan
1 month, 3 weeks agowalkerboh
11 months, 3 weeks agoUA_86
1 year agoAditech
1 year, 2 months agoAditech
1 year, 2 months agojosephsafiran
1 year, 3 months agommhawish
1 year, 3 months agoAbdelmonm
1 year, 4 months agocb4a6c4
1 year, 6 months agoOnly12go
1 year, 7 months agovictory108
1 year, 8 months agoChezQW
1 year, 8 months agoemelba
2 years, 1 month agokevzzz
2 years, 1 month agoKukusha
2 years, 3 months agomrbottomwood
2 years, 3 months agomrbottomwood
2 years, 3 months agomrbottomwood
2 years, 3 months ago