A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.
What should the project manager do?
Only12go
7 months agovictory108
7 months, 3 weeks agopsvexam
9 months agoSteAle
10 months agoBobbie30
1 year, 5 months agoPMPStudent
1 year, 5 months ago