Which of the following would be the best practice in product validation?

  • A. The evaluation criteria should be the same as what was used to measure the requirement.
  • B. There should be two separate measurements for evaluating each functional requirement.
  • C. The measurement of the requirement should be based on the average of two or more evaluations.
  • D. Two or more testers should test the product using the same test cases so that their evaluations are consistent.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
6 months, 2 weeks ago
A is best
upvoted 3 times
...
BA_all_round
9 months, 2 weeks ago
Selected Answer: A
Looks like a use of the term 'validation' in the question and the 'correct answer' are inconsistent with the definitions given in PMI guide: Validation. The assurance that a product, service or system meets the needs of the customer and other identified stakeholders. It often involves acceptance and suitability with external customers. Contrast with Verification. Verification. The evaluation of whether or not a product, service or system complies with a gerulation, requirement, specification, or imposed condition. It is often an internal process.
upvoted 3 times
...
BA_all_round
9 months, 2 weeks ago
Looks like a use of the term 'validation' in the question is inconsistent with the definition given in PMI guide: Validation. Th assurance that a product, service or system meets the needs of the customer and other identified stakeholders. It often involves acceptance and suitability with externla customers. Contrast with Verification. Verification. The evaluation of whether or not a product, service or system complies with a gerulation, requirement, specification, or imposed condition. It is often an internal process.
upvoted 3 times
...
Jillian154
1 year ago
Selected Answer: A
Based on PMBOK, validation is the action of customer or stakeholder in order to complete the accepted deliverable process
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...