A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.
What should the project manager do next?

  • A. Hire a company in country B to perform a quality check before shipment
  • B. Evaluate the procurement contract to determine the agreed-upon specifications
  • C. Escalate the issue to the purchasing department for review
  • D. Add an additional task to cut the received part according to the specifications
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
4 months, 2 weeks ago
Selected Answer: B
For me B is the best approach, as a project manager I will review the procurement specification and trace any errors in miscommunication.
upvoted 1 times
...
4f6ae44
10 months ago
B - Always assess the situation before making a decision
upvoted 2 times
...
Asakthi
1 year, 6 months ago
B evaluate the procurement contract
upvoted 1 times
...
Muntadher
1 year, 6 months ago
Selected Answer: B
need to check what was agreed specification
upvoted 1 times
...
MKWONG
1 year, 7 months ago
Selected Answer: B
procurement contract should able to reflect what was the agreed specification.
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: B
B. Evaluate the procurement contract to determine the agreed-upon specifications
upvoted 1 times
...
meetkamal
2 years, 1 month ago
Selected Answer: B
B is correct answer
upvoted 1 times
...
PMPStudent69
2 years, 1 month ago
Selected Answer: B
B correct
upvoted 1 times
...
Tydp
2 years, 2 months ago
Why didn’t he check before calling to complain….
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...