During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
ductrinh
1 month agowittycroc
2 months agoAgratsant
2 months agovlxx
5 months, 2 weeks agoezzaariyouness
8 months, 4 weeks agoKim222
8 months, 4 weeks agoKim222
8 months, 1 week agotonybuivannghia
9 months, 2 weeks agoductrinh
1 month agoLNX_RM_Admin
11 months, 1 week agoMusaad
1 year, 3 months agoLucky_Cindy
1 year, 6 months agokevzzz
1 year, 6 months agoFyrus
1 year, 6 months agoadingmaki
1 year, 6 months agovictory108
1 year, 8 months agoAsakthi
1 year, 8 months agoAish_
1 year, 8 months agoGinniSingh
1 year, 9 months ago