exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 371 discussion

Actual exam question from PMI's PMP
Question #: 371
Topic #: 1
[All PMP Questions]

During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?

  • A. No more action is required.
  • B. Share this opportunity with another project.
  • C. Further monitor the opportunity.
  • D. Establish a contingency reserve to support the opportunity.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 month ago
Selected Answer: A
hahah please let me know if the sponsor dont want to implement those change. so should we monitor it =))
upvoted 1 times
...
wittycroc
2 months ago
Selected Answer: A
Escalate. This risk response strategy is appropriate when the project team or the project sponsor agrees that an opportunity is outside the scope of the project or that the proposed response would exceed the project manager’s authority. Escalated opportunities are managed at the program level, portfolio level, or other relevant part of the organization, and not on the project level. The project manager determines who should be notified about the opportunity and communicates the details to that person or part of the organization. It is important that ownership of escalated opportunities is accepted by the relevant party in the organization. Opportunities are usually escalated to the level that matches the objectives that would be affected if the opportunity occurred. Escalated opportunities are not monitored further by the project team after escalation, although they may be recorded in the risk register for information.
upvoted 1 times
...
Agratsant
2 months ago
Selected Answer: B
B. Share this opportunity with another project. Following PMP’s risk response strategies, the best action is to share the opportunity with another project, program, or portfolio that can leverage it.
upvoted 1 times
...
vlxx
5 months, 2 weeks ago
Selected Answer: B
If the opportunity is outside the scope of the current project, sharing it with another project or organizational function that can act on it is a logical next step. This ensures that the opportunity is utilized effectively and does not go unaddressed.
upvoted 1 times
...
ezzaariyouness
8 months, 4 weeks ago
Selected Answer: B
Why Not Other Options? A. No more action is required: This would mean letting the opportunity go, which might result in a missed chance for the organization to benefit. C. Further monitor the opportunity: Monitoring an opportunity that is outside of the current project scope doesn’t add value to the current project and doesn’t advance the potential benefits of the opportunity. D. Establish a contingency reserve to support the opportunity: Since the opportunity is outside the project scope, allocating resources or reserves within this project for it would not be appropriate.
upvoted 1 times
...
Kim222
8 months, 4 weeks ago
Selected Answer: C
At first I thought it was A. However, I think the C is solid on the “expanding opportunities to a higher level” part of the problem.
upvoted 1 times
Kim222
8 months, 1 week ago
I Change Option A
upvoted 1 times
...
...
tonybuivannghia
9 months, 2 weeks ago
Selected Answer: C
Although the opportunity is out of scope, but the team decided to add it to risk register and escalate to higher level, so we have to monitor it and get responding from higher level. This is opportunity risk and will increase the value for project.
upvoted 2 times
ductrinh
1 month ago
have you ever escalate to your boss, then you follow to monitor your boss atitude ??
upvoted 1 times
...
...
LNX_RM_Admin
11 months, 1 week ago
Selected Answer: C
I suppose that every records in the risk register needs to be monitored
upvoted 2 times
...
Musaad
1 year, 3 months ago
Selected Answer: A
A is correct you escalate it because it is out of your authority so, monitoring it is waist of time. if a PM suggest an opportunity in your project would you let him monitor it !!
upvoted 3 times
...
Lucky_Cindy
1 year, 6 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
kevzzz
1 year, 6 months ago
Selected Answer: A
Further monitoring is scope creep. The project manager is spending time and money monitoring it. No further action is required.
upvoted 2 times
...
Fyrus
1 year, 6 months ago
Selected Answer: C
Once it is the risk register I guess it's just normal to check it from time to time... it doesn't say that you have to go crazy with that opportunity but keep an eye on it. Do not just pass youR work forward and say "ok, work done"
upvoted 1 times
...
adingmaki
1 year, 6 months ago
7. While the escalation is underway, don't stop working the plan of record. No one can predict for certain the outcome of an escalation, so it's typically best to keep everyone marching together until an official decision has been made. From PMI. It must be C. JUST A TIP. IF YOU ARE NOT SURE JUST DO Q QUICK INTERNET SEARCH LIKE: "insert keyword here" PMI project management
upvoted 3 times
...
victory108
1 year, 8 months ago
Selected Answer: C
C. Further monitor the opportunity
upvoted 1 times
...
Asakthi
1 year, 8 months ago
A. No more action is required.
upvoted 2 times
...
Aish_
1 year, 8 months ago
Selected Answer: A
the project manager should ensure that the opportunity is appropriately evaluated, documented, and communicated to the relevant stakeholders or decision-makers through the established change control and governance processes. So no more action required.
upvoted 1 times
...
GinniSingh
1 year, 9 months ago
Selected Answer: A
the project manager needs to communicate the risk to the new risk owner and ensure that they actively accept responsibility for its management. At this point the risk can be removed from the project’s active Risk Register, and it will be entered into the Risk Register at the level where it belongs.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago